Green Mountain Pump Station Facility Project Information
In this document, you will find details related to the Green Mountain Pump Station Facility project, including pre-bid meeting information, SMWVB goals, accepted certifications, good faith effort plan FAQs, and post-award subcontractor payment reporting system. The content covers various aspects of the project, such as contractors, developers, and key personnel involved, as well as guidelines for meeting SMWVB recognition requirements and the importance of good faith outreach efforts.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
GREEN MOUNTAIN PUMP STATION FACILITY Timothy Ybarra Jr., E.I.T. Master Planning Janie Powell Contract Administrator Lee Niles, PE Pape-Dawson Design Consultant Joe Hernandez, PE KB Homes - Developer Pre-Bid Meeting Monday, October 1, 2018
October 1, 2018 Page 2 Oral statements Meeting will not be binding, nor will they change or affect the IFB or the terms or conditions within the Plans and Specifications of these Projects. Changes, if any,will be addressed in writing only via anAddendum. or discussion during the Pre-Bid Green Mountain Pump Station Facility
October 1, 2018 SMWVB Goal Page 3 Green Mountain Pump Station Facility
October 1, 2018 Accepted SMWVB Certifications Page 4 Minority Business Enterprise (MBE) (Includes AABE; ABE; HABE and NABE) Small Business Enterprise (SBE) Woman-owned Business Enterprise (WBE) Veteran-owned Business Enterprise (Tracked) Green Mountain Pump Station Facility
October 1, 2018 Accepted SMWVB Certification Agency South Central Texas Regional Certification Agency (Includes the Texas Historically Underutilized Business HUB Program) Page 5 Minimum Qualifications for SMWVB recognition: SBE-Certified (even MBEs and WBEs) Local office or local equipment yard Green Mountain Pump Station Facility
October 1, 2018 Good Faith Effort Plan (GFEP) FAQs Page 6 Q: Is the 20% SMWVB goal mandatory? A: No, but we ask prime consultants to do their best with good faith outreach efforts. If the goal is not met, proof of outreach efforts is required with the submittal. Q: What if I am having trouble finding SMWVB subconsultants? A: Please email the SMWVB Program Manager with the scopes of work you are seeking. You will receive lists of local SMWVB-certified firms to contact. Q: What if my business is SMWVB-certified? Do I need to find SMWVB subs? A: If your firm is SMWVB-certified, you will most likely meet the goal. However, the GFEP is a required document, and a good faith outreach effort is still necessary. Q: What if I have questions about the GFEP? A: Please contact the SMWVB Program Manager at 210-233-3420, or at Marisol.Robles@saws.org. GFEP questions can be asked at any time before the submittal is due. Green Mountain Pump Station Facility
October 1, 2018 Page 7 Post Award: Subcontractor Payment & Utilization Reporting (S.P.U.R.) System & Subcontractor Changes https://saws.smwbe.com Green Mountain Pump Station Facility
October 1, 2018 Subcontractor Change Request Any changes in subcontractors or suppliers requires prior approval from SAWS: http://www.saws.org/business_center/contractsol/forms.cfm or http://www.saws.org/business_center/contractsol/forms/SMWBChangeForm.pdf Page 8 Green Mountain Pump Station Facility
October 1, 2018 Bid Overview Page 9 The tri-lateral construction of the Green Mountain Pump Station Facility Project, SAWS Job No. 17-1121. The construction estimate is $8,013,031.00 Completion is scheduled for 450 calendar days Green Mountain Pump Station Facility
October 1, 2018 Contract Requirements Certified Payroll Contractor will be required to submit payroll through the Labor Compliance Program using the LCP Tracker software website on a weekly basis - within 7 days of work week ending. Contractor is required to post Department of Labor wage decisions at the job site. SAWS will conduct interviews with subcontractors and employees at the job site. Interviews are private and confidential. Site visits are random and unannounced. Please ensure subcontractors and employees know their job classification. The prime contractor is responsible for payroll submission regardless of the tier. Page 10 Green Mountain Pump Station Facility
October 1, 2018 Contract Requirements (Continued) Insurance Found in Section 5.7 of the General Conditions. Special requirements on insurance are: Construction w/Pollution and Builder s Risk & XS 2. Insurance must be compliant prior to executing the contract. Selected contractor must be compliant with all other contracts in order for SAWS to award the contract. We will ask for insurance prior to Board award to expedite execution of the contract. Page 11 Green Mountain Pump Station Facility
October 1, 2018 Bid Packet Preparation Contractors should ensure that the bid packet submitted addresses each item requested by SAWS on the checklist. References provided to SAWS must include valid contact information previously verified by the Respondent. Bid Proposals may have several pages of line items. Be careful when calculating extensions. Also, check percentages for Mob and Prep of ROW. Addendums are acknowledged on the Bid Proposal. Do not need copies. Page 12 Green Mountain Pump Station Facility
October 1, 2018 Key Reminders All questions should be sent in writing to the corresponding Contract Administrator by email or fax. Please identify the project by its associated solicitation number. Contractors should not contact the SAWS project engineer, the consultants for this project or any other SAWS staff up until Board award. Late bids will not be accepted and will be returned unopened. If mailing bids, ensure that sufficient time is allowed for the package to reach SAWS. If bids will be delivered in person to SAWS, Respondents should allow sufficient travel time, as well as time to check in at the guard station. Page 13 Green Mountain Pump Station Facility
October 1, 2018 IFB Schedule Page 14 Questions Due October 3, 2018 By 5:00 p.m. Bid Due SAWS Board Award December 2018 October 19, 2018 until 10:00 a.m. Notification of Selected Firm October 2018 Answers Posted October 12, 2018 by 5:00 p.m. Green Mountain Pump Station Facility
October 1, 2018 Additional Reminders Please register through SAWS Vendor Registration Program on the SAWS website at www.saws.org to ensure access to the latest information. To receive updates on specific projects, registered vendors must Subscribe to the project by selecting the project, and clicking Subscribe under the Notify Me box. Page 15 Green Mountain Pump Station Facility
October 1, 2018 Contact Information Page 16 Contact Name Janie Powell Marisol Robles Title Telephone Number 210-233-2443 210-233-3420 Email address Janie.Powell@saws.org Marisol.Robles@saws.org Contract Administrator SMWVB Program Manager Contractors should not contact the SAWS project engineer, the consultants or the developer for this project or any other SAWS staff except those stated above up until Board award. Green Mountain Pump Station Facility
October 1, 2018 Page 17 Image result for questions Thank you! Green Mountain Pump Station Facility