Enhance safety through the reconstruction and upgrades at the Printers Parkway and Parkside Drive roundabout in Colorado Springs. The project aims to reconfigure the intersection, improve storm drain network, enhance pedestrian facilities, realign water mains, and reduce conflict points to address the high accident rating. Federal safety grant funding and community support will help complete the project, ensuring a safer commute for residents and property owners.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Printers Parkway and Parkside Drive Roundabout PUBLIC OPEN HOUSE CONSTRUCTION: SUMMER 2019 KEVIN DIEKELMAN, CITY ENGINEERING
City of Colorado Springs, Public Works Department JACOBS Engineering Group HAYWARD, LLC
Property Owner Resident Work Commute
Project Overview o Reconfigure intersection with a Roundabout o Storm drain network o Pedestrian Improvements o Restripe Approaches o Realign & upgrade water mains
Project Need: Safety! o High Accident Rating o Federal Safety Grant o Reduce conflict points
Project Need: Safety! o High Accident Rating Total Accidents 16 #2 15 14 13 12 11 10 * 9 8 7 6 5 4 3 2 1 Year 2010 2011 * Ranking not calculated or did not appear on the list of the top ranking intersections. * #3 #22 2015 2016 * 2012 * * 2013 * 2017 2014 2018
Project Need: Safety! o Federal Safety Grant Using the 2010 data point, the City applied for and was awarded federal dollars from the Hazard Elimination Safety Program (HES). $624,000 Additional dollars from the City, Springs Utilities, and RTA will complete the Project.
Project Need: Safety! o Reduce conflict points 32 Total Conflict Points 42 Total Conflict Points
42 Total Conflict Points 52 Total Conflict Points
Project Need: Safety! o Reduce conflict points 8 Total Conflict Points
Schedule o Public Outreach o Bid/select construction contractor Summer 2019 o 6-month schedule anticipated