Comprehensive Guide to Risk Management Processes

undefined
 
Managing Risk
 
Chapter 7
undefined
 
Risk Management Process
 
Risk
An uncertain event that, if it occurs, has a positive or
negative effect on project objectives
Risk Management
A proactive attempt to recognize and manage internal
events and external threats that affect the likelihood of
a project’s success
What can go wrong (risk event)
How to minimize the risk event’s impact (consequences)
What can be done before an event occurs (anticipation)
What to do when an event occurs (contingency plans)
 
The Risk Event Graph
 
F
I
G
U
R
E
 
7
.
1
 
Risk Management’s Benefits
 
A proactive rather than reactive approach
Reduces surprises and negative consequences
Prepares the project manager to take advantage
of appropriate risks
Provides better control over the future
Improves chances of reaching project
performance objectives within budget and on
time
The Risk
Management
Process
F
I
G
U
R
E
 
7
.
2
 
Managing Risk
 
Step 1: Risk Identification
Generate a list of possible risks through brainstorming,
problem identification and risk profiling.
Macro risks first, then specific events
Step 2: Risk Assessment
Scenario analysis
Risk assessment matrix
Failure Mode and Effects Analysis (FMEA)
Probability analysis
Decision trees, NPV, and PERT
Semiquantitative scenario analysis
Partial Risk Profile for
Product Development Project
F
I
G
U
R
E
 
7
.
3
 
Risk Breakdown Structure
Risk Assessment Form
F
I
G
U
R
E
 
7
.
4
 
Impact Scales
Risk Severity Matrix
F
I
G
U
R
E
 
7
.
5
 
Managing Risk (cont’d)
 
Step 3: Risk Response Development
Mitigating Risk
Reducing the likelihood an adverse event will occur
Reducing impact of adverse event
Transferring Risk
Paying a premium to pass the risk to another party
Avoiding Risk
Changing the project plan to eliminate the risk or condition
Sharing Risk
Allocating risk to different parties
Retaining Risk
Making a conscious decision to accept the risk
 
Contingency Planning
 
Contingency Plan
An alternative plan that will be used if a possible
foreseen risk event actually occurs
A plan of actions that will reduce or mitigate the
negative impact (consequences) of a risk event
Risks of Not Having a Contingency Plan
Having no plan may slow managerial response
Decisions made under pressure can be potentially
dangerous and costly
Risk Response Matrix
F
I
G
U
R
E
 
7
.
7
 
Risk and Contingency Planning
 
Technical Risks
Backup strategies if chosen technology fails
Assessing whether technical uncertainties can be
resolved
Schedule Risks
Use of slack increases the risk of a late project finish
Imposed duration dates (absolute project finish date)
Compression of project schedules due to a shortened
project duration date
 
Risk and Contingency Planning (cont’d)
 
Costs Risks
Time/cost dependency links: costs increase when problems
take longer to solve than expected.
Deciding to use the schedule to solve cash flow problems
should be avoided.
Price protection risks (a rise in input costs) increase if the
duration of a project is increased.
Funding Risks
Changes in the supply of funds for the project can
dramatically affect the likelihood of implementation or
successful completion of a project.
 
Contingency Funding and Time Buffers
 
Contingency Funds
Funds to cover project risks
—identified and unknown
Size of funds reflects overall risk of a project
Budget reserves
Are linked to the identified risks of specific work packages
Management reserves
Are large funds to be used to cover major unforeseen risks (e.g., change in
project scope) of the total project
Time Buffers
Amounts of time used to compensate for unplanned delays
in the project schedule
 
Contingency Fund Estimate (000s)
 
T
A
B
L
E
 
7
.
1
 
Managing Risk (cont’d)
 
Step 4: Risk Response Control
Risk control
Execution of the risk response strategy
Monitoring of triggering events
Initiating contingency plans
Watching for new risks
Establishing a Change Management System
Monitoring, tracking, and reporting risk
Fostering an open organization environment
Repeating risk identification/assessment exercises
Assigning and documenting responsibility for managing risk
 
Change Management Control
 
Sources of Change
Project scope changes
Implementation of contingency plans
Improvement changes
 
Change Management Control
 
The Change Control Process
Identify proposed changes.
List expected effects of proposed changes on schedule and
budget.
Review, evaluate, and approve or disapprove of changes formally.
Negotiate and resolve conflicts of change, condition, and cost.
Communicate changes to parties affected.
Assign responsibility for implementing change.
Adjust master schedule and budget.
Track all changes that are to be implemented.
The Change
Control Process
F
I
G
U
R
E
 
7
.
8
 
Benefits of a Change Control System
 
1.
Inconsequential changes are discouraged by the formal
process.
2.
Costs of changes are maintained in a log.
3.
Integrity of the WBS and performance measures is
maintained.
4.
Allocation and use of budget and management reserve
funds are tracked.
5.
Responsibility for implementation is clarified.
6.
Effect of changes is visible to all parties involved.
7.
Implementation of change is monitored.
8.
Scope changes will be quickly reflected in baseline and
performance measures.
 
Change
Request
Form
 
F
I
G
U
R
E
 
7
.
9
 
Change
Request
Log
 
F
I
G
U
R
E
 
7
.
1
0
Key Terms
A
v
o
i
d
i
n
g
 
r
i
s
k
B
u
d
g
e
t
 
r
e
s
e
r
v
e
C
h
a
n
g
e
 
m
a
n
a
g
e
m
e
n
t
 
s
y
s
t
e
m
C
o
n
t
i
n
g
e
n
c
y
 
p
l
a
n
M
a
n
a
g
e
m
e
n
t
 
r
e
s
e
r
v
e
M
i
t
i
g
a
t
i
n
g
 
r
i
s
k
R
i
s
k
R
i
s
k
 
p
r
o
f
i
l
e
R
i
s
k
 
B
r
e
a
k
d
o
w
n
 
S
t
r
u
c
t
u
r
e
R
i
s
k
 
s
e
v
e
r
i
t
y
 
m
a
t
r
i
x
S
c
e
n
a
r
i
o
 
a
n
a
l
y
s
i
s
S
h
a
r
i
n
g
 
r
i
s
k
T
i
m
e
 
B
u
f
f
e
r
T
r
a
n
s
f
e
r
r
i
n
g
 
r
i
s
k
undefined
 
PERT and PERT
Simulation
 
Chapter 7 Appendix
 
PERT—Program Evaluation Review
Technique
 
Assumes each activity duration has a range that
statistically follows a beta distribution.
PERT uses three time estimates for each activity:
optimistic, pessimistic, and a weighted average to
represent activity durations.
Knowing the weighted average and variances for each
activity allows the project planner to compute the
probability of meeting different project durations.
 
Activity and Project Frequency
Distributions
 
F
I
G
U
R
E
 
A
7
.
1
 
Activity Time Calculations
 
T
h
e
 
w
e
i
g
h
t
e
d
 
a
v
e
r
a
g
e
 
a
c
t
i
v
i
t
y
 
t
i
m
e
 
i
s
 
c
o
m
p
u
t
e
d
 
b
y
t
h
e
 
f
o
l
l
o
w
i
n
g
 
f
o
r
m
u
l
a
:
 
Activity Time Calculations (cont’d)
 
T
h
e
 
v
a
r
i
a
b
i
l
i
t
y
 
i
n
 
t
h
e
 
a
c
t
i
v
i
t
y
 
t
i
m
e
 
e
s
t
i
m
a
t
e
s
 
i
s
a
p
p
r
o
x
i
m
a
t
e
d
 
b
y
 
t
h
e
 
f
o
l
l
o
w
i
n
g
 
e
q
u
a
t
i
o
n
s
:
 
T
h
e
 
s
t
a
n
d
a
r
d
 
d
e
v
i
a
t
i
o
n
 
f
o
r
 
t
h
e
 
a
c
t
i
v
i
t
y
:
 
T
h
e
 
s
t
a
n
d
a
r
d
 
d
e
v
i
a
t
i
o
n
 
f
o
r
 
t
h
e
 
p
r
o
j
e
c
t
:
 
N
o
t
e
 
t
h
e
 
s
t
a
n
d
a
r
d
 
d
e
v
i
a
t
i
o
n
 
o
f
 
t
h
e
 
a
c
t
i
v
i
t
y
 
i
s
 
s
q
u
a
r
e
d
 
i
n
 
t
h
i
s
 
e
q
u
a
t
i
o
n
;
t
h
i
s
 
i
s
 
a
l
s
o
 
c
a
l
l
e
d
 
v
a
r
i
a
n
c
e
.
 
T
h
i
s
 
s
u
m
 
i
n
c
l
u
d
e
s
 
o
n
l
y
 
a
c
t
i
v
i
t
i
e
s
 
o
n
 
t
h
e
c
r
i
t
i
c
a
l
 
p
a
t
h
(
s
)
 
o
r
 
p
a
t
h
 
b
e
i
n
g
 
r
e
v
i
e
w
e
d
.
 
Activity Times and Variances
 
Probability of Completing the Project
 
The equation below is used to compute the “
Z
” value found in
statistical tables (
Z 
= number of standard deviations from the
mean), which, in turn, tells the probability of completing the
project in the time specified.
 
(
7
.
4
)
 
Hypothetical Network
 
F
I
G
U
R
E
 
A
7
.
2
 
Hypothetical Network (cont’d)
 
F
I
G
U
R
E
 
A
7
.
2
 
(
c
o
n
t
d
)
 
Possible Project Duration
 
F
I
G
U
R
E
 
A
7
.
3
 
Z
 Values
 
T
A
B
L
E
 
A
7
.
3
Slide Note
Embed
Share

Explore the essential aspects of risk management in Chapter 7, covering the risk management process, benefits, risk event graph, and step-by-step procedures for risk identification and assessment. Learn how proactive risk management reduces surprises, enhances control, and improves project performance within constraints.

  • Risk Management
  • Risk Identification
  • Scenario Analysis
  • Project Performance
  • Proactive Approach

Uploaded on Sep 22, 2024 | 1 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Managing Risk Chapter 7

  2. Risk Management Process Risk An uncertain event that, if it occurs, has a positive or negative effect on project objectives Risk Management A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project s success What can go wrong (risk event) How to minimize the risk event s impact (consequences) What can be done before an event occurs (anticipation) What to do when an event occurs (contingency plans)

  3. The Risk Event Graph FIGURE 7.1

  4. Risk Managements Benefits A proactive rather than reactive approach Reduces surprises and negative consequences Prepares the project manager to take advantage of appropriate risks Provides better control over the future Improves chances of reaching project performance objectives within budget and on time

  5. The Risk Management Process FIGURE 7.2

  6. Managing Risk Step 1: Risk Identification Generate a list of possible risks through brainstorming, problem identification and risk profiling. Macro risks first, then specific events Step 2: Risk Assessment Scenario analysis Risk assessment matrix Failure Mode and Effects Analysis (FMEA) Probability analysis Decision trees, NPV, and PERT Semiquantitative scenario analysis

  7. Partial Risk Profile for Product Development Project FIGURE 7.3

  8. Risk Breakdown Structure

  9. Risk Assessment Form FIGURE 7.4

  10. Impact Scales

  11. Risk Severity Matrix FIGURE 7.5

  12. Managing Risk (contd) Step 3: Risk Response Development Mitigating Risk Reducing the likelihood an adverse event will occur Reducing impact of adverse event Transferring Risk Paying a premium to pass the risk to another party Avoiding Risk Changing the project plan to eliminate the risk or condition Sharing Risk Allocating risk to different parties Retaining Risk Making a conscious decision to accept the risk

  13. Contingency Planning Contingency Plan An alternative plan that will be used if a possible foreseen risk event actually occurs A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event Risks of Not Having a Contingency Plan Having no plan may slow managerial response Decisions made under pressure can be potentially dangerous and costly

  14. Risk Response Matrix FIGURE 7.7

  15. Risk and Contingency Planning Technical Risks Backup strategies if chosen technology fails Assessing whether technical uncertainties can be resolved Schedule Risks Use of slack increases the risk of a late project finish Imposed duration dates (absolute project finish date) Compression of project schedules due to a shortened project duration date

  16. Risk and Contingency Planning (contd) Costs Risks Time/cost dependency links: costs increase when problems take longer to solve than expected. Deciding to use the schedule to solve cash flow problems should be avoided. Price protection risks (a rise in input costs) increase if the duration of a project is increased. Funding Risks Changes in the supply of funds for the project can dramatically affect the likelihood of implementation or successful completion of a project.

  17. Contingency Funding and Time Buffers Contingency Funds Funds to cover project risks identified and unknown Size of funds reflects overall risk of a project Budget reserves Are linked to the identified risks of specific work packages Management reserves Are large funds to be used to cover major unforeseen risks (e.g., change in project scope) of the total project Time Buffers Amounts of time used to compensate for unplanned delays in the project schedule

  18. Contingency Fund Estimate (000s) TABLE 7.1

  19. Managing Risk (contd) Step 4: Risk Response Control Risk control Execution of the risk response strategy Monitoring of triggering events Initiating contingency plans Watching for new risks Establishing a Change Management System Monitoring, tracking, and reporting risk Fostering an open organization environment Repeating risk identification/assessment exercises Assigning and documenting responsibility for managing risk

  20. Change Management Control Sources of Change Project scope changes Implementation of contingency plans Improvement changes

  21. Change Management Control The Change Control Process Identify proposed changes. List expected effects of proposed changes on schedule and budget. Review, evaluate, and approve or disapprove of changes formally. Negotiate and resolve conflicts of change, condition, and cost. Communicate changes to parties affected. Assign responsibility for implementing change. Adjust master schedule and budget. Track all changes that are to be implemented.

  22. The Change Control Process FIGURE 7.8

  23. Benefits of a Change Control System Inconsequential changes are discouraged by the formal process. Costs of changes are maintained in a log. Integrity of the WBS and performance measures is maintained. Allocation and use of budget and management reserve funds are tracked. Responsibility for implementation is clarified. Effect of changes is visible to all parties involved. Implementation of change is monitored. Scope changes will be quickly reflected in baseline and performance measures. 1. 2. 3. 4. 5. 6. 7. 8.

  24. Change Request Form FIGURE 7.9

  25. Change Request Log FIGURE 7.10

  26. Key Terms Avoiding risk Budget reserve Change management system Contingency plan Management reserve Mitigating risk Risk Risk profile Risk Breakdown Structure Risk severity matrix Scenario analysis Sharing risk Time Buffer Transferring risk

  27. PERT and PERT Simulation Chapter 7 Appendix

  28. PERTProgram Evaluation Review Technique Assumes each activity duration has a range that statistically follows a beta distribution. PERT uses three time estimates for each activity: optimistic, pessimistic, and a weighted average to represent activity durations. Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations.

  29. Activity and Project Frequency Distributions FIGURE A7.1

  30. Activity Time Calculations The weighted average activity time is computed by the following formula:

  31. Activity Time Calculations (contd) The variability in the activity time estimates is approximated by the following equations: The standard deviation for the activity: The standard deviation for the project: Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed.

  32. Activity Times and Variances

  33. Probability of Completing the Project The equation below is used to compute the Z value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the project in the time specified. (7.4)

  34. Hypothetical Network FIGURE A7.2

  35. Hypothetical Network (contd) FIGURE A7.2 (cont d)

  36. Possible Project Duration FIGURE A7.3

  37. Z Values TABLE A7.3

More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#