Challenges in Monitoring and Measuring Lessons Learned for Pre-Retrofit Analysis

 
Practicalities and challenges of monitoring and
measuring – lessons learned for pre-retrofit analysis
 
Nick Ainger
AgilitySurvey
 
Monitoring overview
 
Energy use and internal/external environments were monitored
Three different systems were trialled
Systems 1 & 2: used customers’ Wi-Fi and were powered by a
mains plug
System 3: is GPRS enabled and hardwired into the mains
All systems required access to the residents’ homes and included:
A CT clamp to monitor electricity consumption
A sensor for temperature, humidity and CO
2
A hub to collect and transmit the data
An external environment sensor
The installation process and equipment used is critical to ensure
the quality of data collected
 
Issues
 
Problems were caused both by limitations of the equipment used
and with residents’ interaction with the kit and the project team
Technical issues were often compounded by lack of resident buy-
in
Resident problems included:
Internet disconnection
Unplugging the kit
Being unable to gain access to repair issues (plugging back in,
changing batteries, reconnecting to Wi-Fi)
 
 
Lesson learned – tenant engagement
 
Residents need to be fully engaged with the project
If incentives are used these should be conditional on
maintaining the equipment and allowing access when needed
There should be some guidance provided with basic
maintenance instructions
A sticker with contact details on the equipment itself is a
good way to ensure residents know who to contact
 
Lesson learned – kit
 
Having a reliable system can mitigate the need for resident
involvement which increases reliability
The third system we used is more robust and has resulted in
fewer issues
The most common issues with the first system were:
Residents broadband being disconnected
Residents unplugging the equipment
By having a system with GPRS connectivity which is hardwired
into the mains these issues are prevented
This was a more involved install process (an electrician was
required) but has resulted in less time being spent rectifying
problems and therefore proved to be more cost effective
 
Conclusion
 
Tenants eager to participate coupled with the latest
self-managing equipment results in sufficient and
meaningful data collection
 
Slide Note
Embed
Share

Practicalities encountered when monitoring energy usage and environments pre-retrofit, including various trial systems used, installation requirements, equipment limitations, and issues with resident engagement. Lessons learned highlight the importance of tenant involvement and the impact of reliable systems on mitigating problems and increasing cost-effectiveness.

  • Challenges
  • Monitoring
  • Lessons Learned
  • Retrofit Analysis
  • Energy Usage

Uploaded on Jul 27, 2024 | 1 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Practicalities and challenges of monitoring and measuring lessons learned for pre-retrofit analysis Nick Ainger AgilitySurvey

  2. Monitoring overview Energy use and internal/external environments were monitored Three different systems were trialled Systems 1 & 2: used customers Wi-Fi and were powered by a mains plug System 3: is GPRS enabled and hardwired into the mains All systems required access to the residents homes and included: A CT clamp to monitor electricity consumption A sensor for temperature, humidity and CO2 A hub to collect and transmit the data An external environment sensor The installation process and equipment used is critical to ensure the quality of data collected

  3. Issues Problems were caused both by limitations of the equipment used and with residents interaction with the kit and the project team Technical issues were often compounded by lack of resident buy- in Resident problems included: Internet disconnection Unplugging the kit Being unable to gain access to repair issues (plugging back in, changing batteries, reconnecting to Wi-Fi)

  4. Lesson learned tenant engagement Residents need to be fully engaged with the project If incentives are used these should be conditional on maintaining the equipment and allowing access when needed There should be some guidance provided with basic maintenance instructions A sticker with contact details on the equipment itself is a good way to ensure residents know who to contact

  5. Lesson learned kit Having a reliable system can mitigate the need for resident involvement which increases reliability The third system we used is more robust and has resulted in fewer issues The most common issues with the first system were: Residents broadband being disconnected Residents unplugging the equipment By having a system with GPRS connectivity which is hardwired into the mains these issues are prevented This was a more involved install process (an electrician was required) but has resulted in less time being spent rectifying problems and therefore proved to be more cost effective

  6. Conclusion Tenants eager to participate coupled with the latest self-managing equipment results in sufficient and meaningful data collection

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#