Castleknock / Mulhuddart Programme of Works 2020

Castleknock / Mulhuddart Programme of Works 2020
Slide Note
Embed
Share

Comprehensive overview of the Castleknock/Mulhuddart Programme of Works 2020 including surface restoration, maintenance, minor works, footpath improvements, traffic management, public lighting, and parks improvement. Details of locations, status, and total budget are provided, along with images showcasing the ongoing projects.

  • Castleknock
  • Mulhuddart
  • Programme of Works
  • Maintenance
  • Improvement

Uploaded on Mar 05, 2025 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. CASTLEKNOCK/MULHUDDART PROGRAMME OF WORKS 2020 Description Item Total 1 Surface Restoration Improvement Works & Maintenance Works 890,000 2 Minor Works Improvement Programme 350,000 3 Traffic Management 250,000 4 Public Lighting 34,000 5 Parks Improvement Works 135,000 TOTAL 1,659,000

  2. Surface Restoration & Maintenance Item Location Description of Works Status 1 R121 Hollywoodrath Road Surface Restoration Tender Awarded 2 R122 Luttrelstown Road Surface Restoration Tender Awarded 3 Castlecurragh Road Surface Restoration Works Complete 4 Ratoath Road, Hollystown Surface Restoration Tender Awarded 5 Riverwood Road Surface Restoration Under review 6 Bramley Walk & View Surface Restoration Tender Published 7 Lohunda Phase 2 Surface Restoration Works Complete 8 Sycamore Avenue Surface Restoration Under review 9 Westway Phase 3 Surface Restoration Works Complete 10 Grove Road Surface Restoration Tender Published 11 Somerton Lane Upgrade surface water line Direct Labour - Works Ongoing Operations Department

  3. Minor Works/Footpath Improvements Item Location Castleknock Village Description of Works Cobblelock - repairs & footpath improvements Cobblelock Status 1 Under Review Blanchardstown Village Main Street Hartstown Area - Cherryfield Estate Huntstown Area - Whitestown Estate Laurel Lodge Area - Castleknock Drive R121 Blanchardstown Road South footpath and cycle path 2 Under Review Works Complete Works Commenced Tender Awarded Footpath Repairs/improvements 3 Footpath Repairs/improvements 4 Footpath Repairs/improvements 5 Footpath Repairs/improvements 6 Under Review Delwood Road - Delwood Park to Tesco Blanchardstown Area - Roselawn Estate/Coolmine Park Mulhuddart Area - Dromheath & Wellview Estate Footpath Repairs/improvements 7 Direct labour Footpath Repairs/improvements 8 Under Review Footpath Repairs/improvements 9 Tender Published Operations Department

  4. Minor Works/Footpath Improvements Item Location Description of Works Status Corduff Area - Corduff Grove Footpath Repairs/improvements 10 Tender Published Castleknock Area - Chesterfield Footpath Repairs/improvements 11 Tender Awarded Auburn Drive, Green & Close Footpath Repairs/improvements 12 Direct Labour Coolmine Boulevard Footpath Repairs/improvements 13 Direct Labour Works Ongoing Glenville Estate Footpath Repairs/improvements 14 Direct Labour Operations Department

  5. Traffic Management Item Location Description of Works Status Traffic Calming Castleknock Drive Ramps x 2 Tender Prepared 1 Speed Cushions x 4 Tender Prepared 2 Allendale to Ravenwood Estate Glenville Road Ramps x 3 Tender Prepared 3 Traffic Signal Installation/ Upgrades Barnewall Road (Ongar) Zebra Crossing Tender Published 1 St. Margaret's Road Pedestrian Signals Tender Published 2 Diswellstown Road Pedestrian Signals or Zebra Crossing Tender Published 3 Operations Department

  6. Traffic Management Ramp Repairs/ Footpath Build Outs Blanchardstown/ Clonsilla Road Junction Accessibility Upgrade 1 Accessibility Upgrade - New drop kerbs, tactile paving, widen footpath on all arms Tender Prepared 2 Manorfields Avenue (both ends) Accessibility Works - New kerbs, install tactile paving, dished areas. Tender Prepared 3 Castleknock Laurels New kerbs, install tactile paving, dished areas. Cushion Repairs Tender Prepared 4 Hollystown/ Tyrrelstown Pecks Lane/the Pines Tender Prepared 5 Extend footpath and dish kerbs, install new tactiles. Tender Prepared Vehicle Activated Signs Clonsilla Road (Between Coolmine & Roselawn) Lower Lucan Road Tender Published 1 Tender Published 2 Operations Department

  7. Public Lighting Item Location Description of Works Status Site visit with Contractor June 1 Cappagh Road at M50 Overpass Install new lighting Materials on order 2 Old Navan Road to St Brigids GAA club Upgrade lighting Materials on order 3 R147 Ashtown to Navan Rd Parkway Upgrade lighting Site visit with Contractor June 4 Willow Wood View Hartstown Install new light Operations Department

  8. Parks Improvements Works Item 1 Location Coolmine Woods Description of Works Develop a woodland wildflower pollinator friendly planting scheme Wildflower & perennial planting to promote bee and butterfly populations in public park and public open spaces Status Planned Q3 2 10 locations Location selection under review 3 Damastown Relining of the carpark at Damastown Pitches Planned Q3 4 St. Patricks Park Upgrade of the plaza planting and path network to the open space Concept & Rationale completed 5 Riverwood Dale Formalise desire line across the open space with tarmac pathway (100m) Regeneration of woodlands Planned Q3 6 Portersgate & Waterville Planned Q4 15 trees planted Feb 2020 Site selection for items underway 7 Hazelbury Park Tree planting programme & installation of exercise equipment 8 Lambourn Park Removal of dangerous, over mature trees & replacement planting Works completed Operations Department

  9. Parks Improvements Works Item Location Description of Works Status Mulhuddart Woods Installation of kissing gate/access barrier 9 Tendered Glenealy Downs Installation of new pathway 10 Planned Q3 Planned Q3 Westhaven & Castlewood openspace Removal of existing concrete pathway and replace 11 Castlewood & Beechwood Close Installation of knee rail & associated bulb planting (100m) Planned Q3 & Q4 12 Aisling Heights/Corduff Formalise desire line with tarmac pathway Planned Q3 13 Parslickstown Formalise desire line across open space with tarmac footpath (80m) Planned Q3 14 Operations Department