Advanced Virgo Squeezing Working Group Overview

 AdV squeezing
INFN Referee  Cascina  July  23,  2018
1
 
AdV squeezing
Jean-Pierre Zendri
On behalf of the squeezing working group
Layout
2
INFN Referee  Cascina  July  23,  2018
Frequency Independent Squeezing (O3)
Installation
Commissioning
Frequency Dependent Squeezing (O4)
Status and planning
AdV-FIS
Squeezed
SDB1
DetLab
AEI
Squeez.
Injection
bench
SDB2
Electronics
Clean room
 ≥1000
Acoustic enclosure
 
External bench 
hosting the squeezer 
3D-view
INFN Referee  Cascina  July  23,  2018
3
4
Matching
telescope
External PLL
(auto-) alignment
Camera 1
FIS: Optical layout
Squeezer
r
 
INFN
 
INFN
 
INFN
 
INFN
 
INFN
 
Internal PLL
 
INFN
INFN Referee  Cascina  July  23,  2018
Microphone
Accelerometers
Seismometers
Thermometers
 
INFN
The AEI squeezer in AdV
5
INFN Referee  Cascina  July  23,  2018
Friday 12 January
Sunday  14 January
 
Example: with air blowers ON and
moderate green power
 
8 dB
 
10.5 dB
 
(9.0 dB
prod.
 )
The Hannover  results  reproduced in Cascina
6
FIS: telescope and alignment
Squeezer box
Fast shutter
Motorized steering
Camera2
Camera1
 
mode matching of more
than <50% has never
been achieved
INFN Referee  Cascina  July  23,  2018
Faraday isolators
7
INFN Referee  Cascina  July  23,  2018
In vacuum bench test (
VIR-0084A-18
)
 
G. Pillant, E. Genin, C. De Rossi
Throughput: (99±0.2)%
Isolation > 40 dB
«Vacuum «faraday before assembling on SDB1
Installed on SDB1 (
entry#40626
)
«Only» the motorized shutter
the half wave plate and  the Peltier
element have been connected
Double stage in air faraday on the squeezer
In vacuum Faraday
In air Faraday
Bench test before assembly
(
DCC-G1800468-v1
)
Throughput: (99.4±0.2)%
Installed on the squeezer bench
(
entry#
41211
)
FIS: Electronics
8
INFN Referee  Cascina  July  23,  2018
Squeezer Controls: Rack5
The analog squeezer control system
provided by AEI.
DAQ based monitor and triggering
system and additional digital loops
RACK-5
2  PLL boards  (internal and external
PLL).
8 DDS (rf) channels locked to the
main Virgo time distribution
All the motors and translation stage
drivers.
RACK-4
 
INFN
FIS: Infrastructures
9
INFN Referee  Cascina  July  23,  2018
Entry#
40854
Entry#
40854
Plexiglas box
Plexiglas  connection pipe
Acoustic enclosure
Big Flange and Viewport
10
INFN Referee  Cascina  July  23,  2018
SDB1 Viewport
Dust contamination issue
The viewport has been substituted during the last det tower venting
Entry#40683
Squeezer bench
Entry#40681
FIS: BAB versus OMC matching
11
INFN Referee  Cascina  July  23,  2018
Although some attempts have already been made, a mode
matching of more than <50% has never been achieved (entry
#
41542,41521,40668).
The measured  diameter of the beam comming from the ITF is
30% lower than the expected  one (entry #
41689,41746)
This required to change the geometry of the telescope in
reflection.
 
Entry#41131
Next week expected two shifts
with ITF
FIS: PLLs
12
INFN Referee  Cascina  July  23,  2018
Internal PLL 
between the squeezer main  and CC lasers
 
Extetrnal PLL 
between the squeezer and AdV main lasers
Res. phase noise 
7 mrad
80 MHz
 
Res. phase noise 
15-30 mrad
 
7 MHz
 
Ext PLL off
 
Ext PLL on
Fiber phase noise
13
INFN Referee  Cascina  July  23,  2018
 
The phase noise induced by  termo-acoustic pick-up of the  PM fiber
has been measured
PLL- residual phase noise (<15 mrad)
 
Fiber phase noise (180 mrad)
First Injection test (May 2018)
14
INFN Referee  Cascina  July  23,  2018
 
Measured time
delay 1 ms
No  squeezed light effect (ITF not shot noise limited)
First test of the Coherent Control Loop
 
Unitary gain bandwidth 140 Hz (required at least 1 kHz) mainly limited by the
ms time delay induced by digital demodulation plus DAC
Residual phase noise order of 60 mrad (target 30 mrad)
SDB1
 
INFN
CC beam 7MHz offset
 co propagating with the
squeezed beam
Achievement  of the project targets
15
INFN Referee  Cascina  July  23,  2018
15
  
Optical Losses
 Squeezing ellipse jitter
Early
August ?
Target:
 30 mrad
  
Achieved:
 70 mrad (mainly for DAC  time latency)
FI: short term activities
16
INFN Referee  Cascina  July  23,  2018
Early August  (2-3)
Mode matching and alignment with ITF (
INFN
)
Hierarchical autolocking of the PLLs using Metatron (EGO &
INFN
)
End of August (21-24)
Squeezed light  injection in the dark port
Test of the CC
Test of the autoalignment system.
Prerequirements:
 ITF stable and shot noise limited
FIS Target sensitivity
17
INFN Referee  Cascina  July  23,  2018
17
The injected squeezing degree  must be kept below 4-5  dB
The expected HF gain is thus 3-4 dB
Frequency Dependent Squeezing
18
INFN Referee  Cascina  July  23,  2018
18
FDS
AdV+ Phase I
19
INFN Referee  Cascina  July  23,  2018
19
Frequency dependent
Squeezing with Filter Cavity
Preliminary time schedule
INFN Referee  Cascina  July  23,  2018
20
https://svn.ego-gw.it/svn/AdvVirgo/AdV_Squeezing/
Conceptual design
: basic design and the list of requests to be met
FDS next steps
INFN Referee  Cascina  July  23,  2018
21
“ Items and interest of groups that are listed in this document have been communicated in the
past.
Please identify missing items.
Indicate participation of your group to certain items
·         Specify the resources (financial, person power, in-kind) that you can contribute
·         Specify the resources that you request from EGO Council to deliver your contribution
STEP1: Deadline July 30 30
Meeting of group leaders scheduled for early August. Then roles and responsibilities will be
discussed
The high level WBS will be presented to the Council
STEP2 : Early August
STEP3 : September 23
FDS preliminary requirements
22
INFN Referee  Cascina  July  23,  2018
Target
: 7-8 dB of HF improvement without degrading low
frequency for both AdV and AdV+
 
Optical losses
 
Needs of a strategy to reduce mode mismatch an misalignment .
This R&D activity have to be included on the project!
 
A significant
reduction of losses
is required
Filter cavity  lenght
INFN Referee  Cascina  July  23,  2018
23
Filter cavity losses : decrease with FC lenght.
Relevant parameter: round trip losses assumed
20 ppm
Mode mismatch contribution
: length
independent.  Assumed 1%
Residual cavity displacement noise: scales as
the inverse of the cavity lenght
Noise budget contributions
 
FC design 
(VIR-0312A-18)
The best compromise for the
AdV FC length is about
300-500 meters
Strain sensitivity
Noise budget
sensitivity to the FC  parameters
INFN Referee  Cascina  July  23,  2018
24
Excess of losses in the cavity
Mode mismatch
NS-NS
NS-NS
BH-BH
BH-BH
In air or in vacuum squeezer?
INFN Referee  Cascina  July  23,  2018
25
Dettails on 
VIR-0875B-17
S1FI and S1F2 are mandatory
SSB1 traking of SDB1  required
With a linear OPO the IFI is
always required regardless if
the OPO is suspended  or not
The decision is postponed until we will test the  model and estimate the
value of some parameters with measures on the FIS
Preliminary FDS layout
26
INFN Referee  Cascina  July  23,  2018
Squeezer
North arm
Injection
Optics
Filter Cavity
Input mirror
M.Tacca et all.
 VIR-0703A-17
 
Squeezer in air
 
Squeezer in vacuum
 
On SDB1
Minitower
Simpler Susp.
Alignment bench
‘moderate’ civil works needed 
(TBD by Civil_team)
1)
‘ Hole’ opening (sandwich wall 5 cm thick), and
2)
displacement of HVAC channel
2) ‘passage‘ opening (in ‘not critical’ concrete walls)
3) Storage-room  area upgrading
4) Shift the ‘tube crossing stairs
 Infrastructure modifications
Preliminary design (sligthly changed respect the original design)
INFN Referee  Cascina  July  23,  2018
27
FDS: FC infrastructures
28
INFN Referee  Cascina  July  23,  2018
Planimetry
End Mirror
The tunnel roof
has   to be raised
300
Infrastructure meeting
July 10 2018
The FC «Y» position
has been fixed so the
FC lenght is defined
Two possible scenarios
for «X»position
FDS: FC suspensions
29
INFN Referee  Cascina  July  23,  2018
2300 mm
Kick-Off meeting on May 7th, design started on May 10th
Production drawings are in progress
(VIR-0401A-18)
.
FDS: Cavity controls (IR)
30
Virgo Week  July   July  11  ,  2018
IR locking scheme (
VIR-0398A-18)
Alternative scheme: Use the CC sidebands for the FC
alignment and locking (
VIR-0329A-18
)
Frequency offset:
n*FSR+Detuning 
~ GHz
Cavity Finesse 8000
Need of GHz PLL
INFN Referee  Cascina  July  23,  2018
31
FDS: Cavity controls (green)
Locking with auxiliary green beam  (
VIR-0399A-18, VIR-0329A-18 , VIR-
0400A-18 
)
Integrated scheme
In air squeezer
Inj minitower
Ctrl microtower
FDS: INFN R&D and activities
INFN Referee  Cascina  July  23,  2018
32
Richieste divise
FDS
: attività specifiche per FDS
FDS&EPR
: attività che hanno applicazioni in entrambe le due
linee di ricerca
Sensing 
Mode Mismatch Using Existing WFS
INFN Referee  Cascina  July  23,  2018
33
Benefit of mode converter with quadrant photodiodes
Ability to measure mode mismatch using existing QPD WFS
Mode converter preserves cavity misalignment signals.
No new electronics or channels are needed.
QPDs are easier to align than BPDs.
Compared to BPDs, QPDs are off-the-shelf and have a much
better matched quadrant capacities on optical gains.
Only one mode converter, followed by normal Gouy phase
telescopes for each sensor is needed to sense all four
alignment and two mode-match degrees of freedom
The only optical component critically sensitive to beam size is
the mode converter itself. It is much easier to change than
the segment size of (multiple) BPDs
Credit to Fabian Magaña-Sandoval
Sensing 
Mode Mismatch Using Existing PD
INFN Referee  Cascina  July  23,  2018
34
Primo prototipo  di lente elettro-ottica realizzato.
La costruzione del  set-up sperimentale per il primo test è in fase conclusiva
Slide Note
Embed
Share

The Advanced Virgo (AdV) project involves various activities related to squeezing technology, optical layouts, Faraday isolators, and electronics. The project includes components like the squeezer, clean room, detectors, telescopes, and alignment systems. The installation, commissioning, and status planning are detailed in the INFN Referee reports from Cascina, dated July 23, 2018. The project also aims to achieve specific results like matching telescope alignments and Faraday isolator performance. Various equipment and control systems are utilized to ensure the project's success.

  • Advanced Virgo
  • Squeezing Technology
  • Optical Layouts
  • Faraday Isolators
  • Electronics

Uploaded on Sep 13, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. AdV squeezing AdV squeezing Jean-Pierre Zendri On behalf of the squeezing working group INFN Referee Cascina July 23, 2018 1

  2. Layout Frequency Independent Squeezing (O3) Installation Commissioning Frequency Dependent Squeezing (O4) Status and planning INFN Referee Cascina July 23, 2018 2

  3. AdV-FIS External bench hosting the squeezer Clean room 1000 DetLab 3D-view SDB2 Electronics Injection bench SDB1 AEI Squeez. Acoustic enclosure Squeezed INFN Referee Cascina July 23, 2018 3

  4. FIS: Optical layout INFN Camera 2 INFN External PLL INFN Matching telescope INFN Camera 1 INFN Microphone Accelerometers Seismometers Thermometers Squeezerr INFN (auto-) alignment Internal PLL INFN INFN Referee Cascina July 23, 2018 4

  5. The AEI squeezer in AdV Friday 12 January Sunday 14 January The Hannover results reproduced in Cascina Example: with air blowers ON and moderate green power 10.5 dB 8 dB (9.0 dBprod.) INFN Referee Cascina July 23, 2018 5

  6. FIS: telescope and alignment mode matching of more than <50% has never been achieved Motorized steering Squeezer box Fast shutter Camera1 Camera2 INFN Referee Cascina July 23, 2018 6

  7. Faraday isolators In vacuum Faraday Vacuum faraday before assembling on SDB1 In vacuum bench test (VIR-0084A-18) Throughput: (99 0.2)% Isolation > 40 dB Installed on SDB1 (entry#40626) Only the motorized shutter the half wave plate and the Peltier element have been connected G. Pillant, E. Genin, C. De Rossi Double stage in air faraday on the squeezer In air Faraday Bench test before assembly (DCC-G1800468-v1) Throughput: (99.4 0.2)% Installed on the squeezer bench (entry#41211) INFN Referee Cascina July 23, 2018 7

  8. FIS: Electronics RACK-5 The analog squeezer control system provided by AEI. DAQ based monitor and triggering system and additional digital loops RACK-4 INFN 2 PLL boards (internal and external PLL). 8 DDS (rf) channels locked to the main Virgo time distribution All the motors and translation stage drivers. Squeezer Controls: Rack5 INFN Referee Cascina July 23, 2018 8

  9. FIS: Infrastructures Plexiglas box Entry#40854 Entry#40854 Acoustic enclosure Plexiglas connection pipe INFN Referee Cascina July 23, 2018 9

  10. Big Flange and Viewport Dust contamination issue SDB1 Viewport Entry#40683 Squeezer bench Entry#40681 The viewport has been substituted during the last det tower venting INFN Referee Cascina July 23, 2018 10

  11. FIS: BAB versus OMC matching Although some attempts have already been made, a mode matching of more than <50% has never been achieved (entry #41542,41521,40668). The measured diameter of the beam comming from the ITF is 30% lower than the expected one (entry #41689,41746) This required to change the geometry of the telescope in reflection. Entry#41131 Next week expected two shifts with ITF INFN Referee Cascina July 23, 2018 11

  12. FIS: PLLs Internal PLL between the squeezer main and CC lasers Ext PLL on Res. phase noise 7 mrad Ext PLL off 80 MHz Extetrnal PLL between the squeezer and AdV main lasers Res. phase noise 15-30 mrad 7 MHz INFN Referee Cascina July 23, 2018 12

  13. Fiber phase noise The phase noise induced by termo-acoustic pick-up of the PM fiber has been measured PLL- residual phase noise (<15 mrad) Fiber phase noise (180 mrad) INFN Referee Cascina July 23, 2018 13

  14. First Injection test (May 2018) No squeezed light effect (ITF not shot noise limited) First test of the Coherent Control Loop CC beam 7MHz offset co propagating with the squeezed beam SDB1 Measured time delay 1 ms INFN Unitary gain bandwidth 140 Hz (required at least 1 kHz) mainly limited by the ms time delay induced by digital demodulation plus DAC Residual phase noise order of 60 mrad (target 30 mrad) INFN Referee Cascina July 23, 2018 14

  15. Achievement of the project targets Optical Losses Early August ? Squeezing ellipse jitter Target: 30 mrad Achieved: 70 mrad (mainly for DAC time latency) INFN Referee Cascina July 23, 2018 15 15

  16. FI: short term activities Prerequirements: ITF stable and shot noise limited Early August (2-3) Mode matching and alignment with ITF (INFN) Hierarchical autolocking of the PLLs using Metatron (EGO & INFN) End of August (21-24) Squeezed light injection in the dark port Test of the CC Test of the autoalignment system. INFN Referee Cascina July 23, 2018 16

  17. FIS Target sensitivity The injected squeezing degree must be kept below 4-5 dB The expected HF gain is thus 3-4 dB INFN Referee Cascina July 23, 2018 17 17

  18. Frequency Dependent Squeezing FDS AdV SR 120 Mpc AdV+ (Phase I) SR+FDS 150 Mpc SR+FDS+NN 160 Mpc INFN Referee Cascina July 23, 2018 18 18

  19. AdV+ Phase I Frequency dependent Squeezing with Filter Cavity INFN Referee Cascina July 23, 2018 19 19

  20. Preliminary time schedule Conceptual design: basic design and the list of requests to be met https://svn.ego-gw.it/svn/AdvVirgo/AdV_Squeezing/ INFN Referee Cascina July 23, 2018 20

  21. FDS next steps STEP1: Deadline July 30 30 Items and interest of groups that are listed in this document have been communicated in the past. Please identify missing items. Indicate participation of your group to certain items Specify the resources (financial, person power, in-kind) that you can contribute Specify the resources that you request from EGO Council to deliver your contribution STEP2 : Early August Meeting of group leaders scheduled for early August. Then roles and responsibilities will be discussed STEP3 : September 23 The high level WBS will be presented to the Council INFN Referee Cascina July 23, 2018 21

  22. FDS preliminary requirements Target: 7-8 dB of HF improvement without degrading low frequency for both AdV and AdV+ A significant reduction of losses is required Optical losses Needs of a strategy to reduce mode mismatch an misalignment . This R&D activity have to be included on the project! INFN Referee Cascina July 23, 2018 22

  23. Filter cavity lenght Noise budget Noise budget contributions Filter cavity losses : decrease with FC lenght. Relevant parameter: round trip losses assumed 20 ppm Mode mismatch contribution: length independent. Assumed 1% Residual cavity displacement noise: scales as the inverse of the cavity lenght FC design (VIR-0312A-18) The best compromise for the AdV FC length is about 300-500 meters Strain sensitivity INFN Referee Cascina July 23, 2018 23

  24. sensitivity to the FC parameters Excess of losses in the cavity NS-NS BH-BH Mode mismatch BH-BH NS-NS INFN Referee Cascina July 23, 2018 24

  25. In air or in vacuum squeezer? Dettails on VIR-0875B-17 S1FI and S1F2 are mandatory SSB1 traking of SDB1 required With a linear OPO the IFI is always required regardless if the OPO is suspended or not The decision is postponed until we will test the model and estimate the value of some parameters with measures on the FIS 25 INFN Referee Cascina July 23, 2018

  26. Preliminary FDS layout Injection Optics Input mirror Squeezer M.Tacca et all. VIR-0703A-17 Squeezer in air Squeezer in vacuum On SDB1 Minitower Simpler Susp. Alignment bench INFN Referee Cascina July 23, 2018 26

  27. Infrastructure modifications Preliminary design (sligthly changed respect the original design) moderate civil works needed (TBD by Civil_team) 1) Hole opening (sandwich wall 5 cm thick), and 2) displacement of HVAC channel H = 2.9m 2) passage opening (in not critical concrete walls) 3) Storage-room area upgrading 4 4) Shift the tube crossing stairs 2 Cryotrap/valve dismount area 3 Crane area (benches , minitowers...) 1 INFN Referee Cascina July 23, 2018 27

  28. FDS: FC infrastructures The tunnel roof has to be raised Infrastructure meeting July 10 2018 The FC Y position has been fixed so the FC lenght is defined Two possible scenarios for X position Planimetry End Mirror 300 INFN Referee Cascina July 23, 2018 28

  29. FDS: FC suspensions Kick-Off meeting on May 7th, design started on May 10th Production drawings are in progress (VIR-0401A-18). 2300 mm INFN Referee Cascina July 23, 2018 29

  30. FDS: Cavity controls (IR) IR locking scheme (VIR-0398A-18) Cavity Finesse 8000 Frequency offset: n*FSR+Detuning ~ GHz Need of GHz PLL Alternative scheme: Use the CC sidebands for the FC alignment and locking (VIR-0329A-18) Virgo Week July July 11 , 2018 30

  31. FDS: Cavity controls (green) Locking with auxiliary green beam (VIR-0399A-18, VIR-0329A-18 , VIR- 0400A-18 ) Integrated scheme Ctrl microtower Inj minitower In air squeezer INFN Referee Cascina July 23, 2018 31

  32. FDS: INFN R&D and activities Richieste divise FDS: attivit specifiche per FDS FDS&EPR: attivit che hanno applicazioni in entrambe le due linee di ricerca INFN Section Genova Napoli Padova Roma II TIFPA Main activity Optical design, Beam pointing and in vacuum optics Optical design, In vacuum optics MM telescopes PLLs, Mode matching sensing with PD and actuation Abberation and higher order modes control Mode matching sensing with QPD and actuation RomaI Perugia Payload,.. Constr. Next year Magnets, hears, wires INFN Referee Cascina July 23, 2018 32

  33. Sensing Mode Mismatch Using Existing WFS Benefit of mode converter with quadrant photodiodes Ability to measure mode mismatch using existing QPD WFS Mode converter preserves cavity misalignment signals. No new electronics or channels are needed. QPDs are easier to align than BPDs. Compared to BPDs, QPDs are off-the-shelf and have a much better matched quadrant capacities on optical gains. Only one mode converter, followed by normal Gouy phase telescopes for each sensor is needed to sense all four alignment and two mode-match degrees of freedom The only optical component critically sensitive to beam size is the mode converter itself. It is much easier to change than the segment size of (multiple) BPDs Laser EOM Thermal Lens Actuators Optical Cavity BPDs Gouy Phase Telescopes OR PDH Lock Alignment and Mode Matching Focusing Lenses Mode Converter QPDs Gouy Phase Telescopes Demodulation and Feedback Electronics Credit to Fabian Maga a-Sandoval INFN Referee Cascina July 23, 2018 33

  34. Sensing Mode Mismatch Using Existing PD Primo prototipo di lente elettro-ottica realizzato. La costruzione del set-up sperimentale per il primo test in fase conclusiva INFN Referee Cascina July 23, 2018 34

Related


More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#