The Ashumet Park Common Land Project aims to transform Lot 8 into a multi-use community area in Ashumet Valley. The project includes three phases: Land Survey, Land Clearing, and Grass Installation. Phase 1 involved conducting a land survey, while Phase 2 focused on land clearing by removing trees and stumps. The final phase includes hydroseeding and grass installation. The anticipated total cost for the project is $13,750.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
ASHUMET PARK Common Land Project
Common Land Project Overview 1.2 ACRES 3 PHASE PROJECT (w/ potential for future improvements) INTENT: To make improvements to Lot 8 which sits at the southeast corner of Ashumet Valley and revitalize what was a long-standing playground to a multi-use community area ideal for Annual Meetings
Common Land Project Overview Phase 1: Survey Phase 2: Land Clearing Phase 3: Grass Installation
PHASE 1- Land Survey Land Survey was conducted in Nov 2018 Stake/markers laid to delineate the property line Several encroachments that have since been resolved
PHASE 2- Land Clearing Peter J Govoni Landservices Cut and chip all trees as discussed Remove all woodchips and logs from site Excavate stumps and dispose of stumps off-site Haul back 100 yards of wood chips and dump on-site at no charge Total: $9,250 Deposit of $4,625
PHASE 3- Grass/Hydroseed Installment Hydroseed Hydroseeding averages $2,000 per acre Grass Seed Avg $900 per acre for seed Avg $180 Starter Fertilizer
OVERALL ANTICIPATED COST Phase 1- Phase 2- Phase 3- Total: $13,750.00 est $2,500.00 $9,250.00 $2,000.00 est (already invested) (already invested)