West Midlands Freight GLOSA Trial Project Overview

Slide Note
Embed
Share

The West Midlands Freight GLOSA Trial project, led by Andy Radford, aims to implement Green Light Optimal Speed Advisory (GLOSA) in the region. It focuses on improving traffic flow and reducing emissions by utilizing existing infrastructure, demonstrating interoperability between C-ITS systems, and enhancing signal priority requests. The project timeline includes activities like approvals, development, and testing phases to achieve safer roads, reliable journey times, and better traffic management in the West Midlands.


Uploaded on Aug 19, 2024 | 2 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. West Midlands Freight GLOSA Trial Andy Radford

  2. Project Definition Birmingham Solihull Coventry MOVA Bus Priority SCOOT Joint SCOOT/ MOVA Greenwave GLOSA UK CITE openstreetmap.org

  3. Aims and Objectives GLOSA in an adaptive control environment. Utilising Existing Infrastructure (4G and Wifi) Can simple changes be made to that environment that improve GLOSA accuracy Can we demonstrate interoperability between C-ITS systems (i.e. from Birmingham to Coventry) Can we demonstrate signal priority requests

  4. WM GLOSA TRIAL Project Data Flows Signal information from On street cabinets sent to Traffic control centre either Via direct link to controller or SCOOT messages Historical Services Prediction Prediction provide via 4G or using existing on-street wifi Antennas FVD Signal Requests

  5. Outcomes Safer Roads More Reliable Journey Times Reduced Emissions Better Reduced Traffic Noise management of network More Less Driver Frustration innovation in WM Improved Modelling and Prediction Better Policy

  6. Programme Time Period Activity April June 2017 Approvals and Procurement July September 2017 Server Side Development September October 2017 App Development November December 2017 Testing Phase 1 December 2017 Refine and Fix January 2018 Testing Phase 2 February March 2018 Results and Dissemination

Related


More Related Content