Robustness Requirements for Electricity Generation Facilities

 
APPENDIX 1.C
ROBUSTNESS REQUIREMENTS
FOR ELECTRICITY GENERATION
FACILITIES
 
N
e
t
w
o
r
k
 
C
o
d
e
 
o
n
 
R
e
q
u
i
r
e
m
e
n
t
s
 
f
o
r
 
G
r
i
d
 
C
o
n
n
e
c
t
i
o
n
A
p
p
l
i
c
a
b
l
e
 
t
o
 
a
l
l
 
G
e
n
e
r
a
t
o
r
s
 
(
R
f
G
)
 
02-07-2019
 
16/05118-100
 
1
 
Lars Højbjerg Nielsen
 
 
This is a translation. In case of inconsistencies, the Danish version applies.
 
FUTURE ROBUSTNESS REQUIREMENTS
 
Requirements for t
clear
 and U
ret
 for generation facilities connected to the distribution grid are described below:
 
t
c
l
e
a
r
 
=
 
2
5
0
 
m
s
 
a
p
p
l
i
e
s
 
t
o
 
a
l
l
 
g
e
n
e
r
a
t
i
o
n
 
f
a
c
i
l
i
t
i
e
s
 
o
f
 
t
y
p
e
s
 
B
 
a
n
d
 
C
 
a
s
 
w
e
l
l
 
a
s
 
t
y
p
e
 
D
U
r
e
t
 
=
 
0
.
3
 
p
.
u
.
 
a
p
p
l
i
e
s
 
t
o
 
a
l
l
 
s
y
n
c
h
r
o
n
o
u
s
 
g
e
n
e
r
a
t
i
o
n
 
f
a
c
i
l
i
t
i
e
s
 
o
f
 
t
y
p
e
s
 
B
 
a
n
d
 
C
 
a
s
 
w
e
l
l
 
a
s
 
t
y
p
e
 
D
U
r
e
t
 
=
 
0
.
1
5
 
p
.
u
.
 
a
p
p
l
i
e
s
 
t
o
 
a
l
l
 
a
s
y
n
c
h
r
o
n
o
u
s
 
g
e
n
e
r
a
t
i
o
n
 
f
a
c
i
l
i
t
i
e
s
 
o
f
 
t
y
p
e
s
 
B
 
a
n
d
 
C
 
a
s
 
w
e
l
l
 
a
s
 
t
y
p
e
 
D
 
Requirements for t
clear
 and U
ret
 for generation facilities connected to the transmission grid are described below:
 
t
c
l
e
a
r
 
=
 
1
5
0
 
m
s
 
a
p
p
l
i
e
s
 
t
o
 
f
o
r
 
a
l
l
 
t
y
p
e
 
D
 
g
e
n
e
r
a
t
i
o
n
 
f
a
c
i
l
i
t
i
e
s
 
c
o
n
n
e
c
t
e
d
 
t
o
 
t
h
e
 
t
r
a
n
s
m
i
s
s
i
o
n
 
g
r
i
d
U
r
e
t
 
=
 
0
.
0
 
p
.
u
.
 
a
p
p
l
i
e
s
 
t
o
 
a
l
l
 
t
y
p
e
 
D
 
g
e
n
e
r
a
t
i
o
n
 
f
a
c
i
l
i
t
i
e
s
 
c
o
n
n
e
c
t
e
d
 
t
o
 
t
h
e
 
t
r
a
n
s
m
i
s
s
i
o
n
 
g
r
i
d
The FRT requirements stated apply to both symmetrical and asymmetrical fault types. The positive voltage sequence
component must be considered in any voltage evaluation.
 
 
02-07-2019
 
16/05118-100
 
2
 
Requirements for fault-ride-through properties
 
FRT REQUIREMENTS FOR SYNCHRONOUS
(SGPM) FACILITIES CONNECTED TO THE
DISTRIBUTION GRID IN DK1 (CE) AND DK2 (N)
 
02-07-2019
 
16/05118-100
 
3
 
Types B, C and D (< 110 kV) facilities
 
02-07-2019
 
16/05118-100
 
4
 
FRT REQUIREMENTS FOR ASYNCHRONOUS
(PPM) FACILITIES CONNECTED TO THE
DISTRIBUTION GRID IN DK1 (CE) AND DK2 (N)
 
Types B, C and D (< 110 kV) facilities
 
FRT REQUIREMENTS FOR SYNCHRONOUS
(SGPM) FACILITIES CONNECTED TO THE
TRANSMISSION GRID IN DK1 (CE)
 
02-07-2019
 
16/05118-100
 
5
 
Type D facilities connected > 110 kV
 
FRT REQUIREMENTS FOR ASYNCHRONOUS
(PPM) FACILITIES CONNECTED TO THE
TRANSMISSION GRID IN DK1 (CE)
 
02-07-2019
 
16/05118-100
 
6
 
Type D facilities connected > 110 kV
 
02-07-2019
 
16/05118-100
 
7
 
FRT REQUIREMENTS FOR SYNCHRONOUS
(SGPM) FACILITIES CONNECTED TO THE
TRANSMISSION GRID IN DK2 (N)
 
Type D facilities connected > 110 kV
 
FRT REQUIREMENTS FOR ASYNCHRONOUS
(PPM) FACILITIES CONNECTED TO THE
TRANSMISSION GRID IN DK2 (N)
 
02-07-2019
 
16/05118-100
 
8
 
Type D facilities connected > 110kV
Slide Note
Embed
Share

The document outlines robustness requirements for electricity generation facilities, covering fault-ride-through properties, clear time and voltage parameters for different types of generation facilities connected to both the distribution grid and transmission grid. Specific requirements for synchronous and asynchronous facilities are detailed, including voltage and time parameters for different fault scenarios.

  • Robustness
  • Electricity Generation
  • Grid Connection
  • Fault Ride Through
  • Voltage Parameters

Uploaded on Sep 14, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. APPENDIX 1.C ROBUSTNESS REQUIREMENTS FOR ELECTRICITY GENERATION FACILITIES Network Code on Requirements for Grid Connection Network Code on Requirements for Grid Connection Applicable to all Generators (RfG) Applicable to all Generators (RfG) Lars H jbjerg Nielsen This is a translation. In case of inconsistencies, the Danish version applies. 16/05118-100 02-07-2019 1

  2. FUTURE ROBUSTNESS REQUIREMENTS Requirements for fault-ride-through properties Requirements for tclear and Uret for generation facilities connected to the distribution grid are described below: tclear = 250 ms applies to all generation facilities of types B and C Uret = 0.3 p.u. applies to all synchronous generation facilities of types B and C Uret = 0.15 p.u. applies to all asynchronous generation facilities of types B and C types B and C as well as type D type D types B and C as well as type D type D types B and C as well as type D type D Requirements for tclear and Uret for generation facilities connected to the transmission grid are described below: tclear = 150 ms applies to for all type D Uret = 0.0 p.u. applies to all type D The FRT requirements stated apply to both symmetrical and asymmetrical fault types. The positive voltage sequence component must be considered in any voltage evaluation. type D generation facilities connected to the transmission grid type D generation facilities connected to the transmission grid 16/05118-100 02-07-2019 2

  3. FRT REQUIREMENTS FOR SYNCHRONOUS (SGPM) FACILITIES CONNECTED TO THE DISTRIBUTION GRID IN DK1 (CE) AND DK2 (N) Types B, C and D (< 110 kV) facilities Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0.3 t tclear clear: : 0.25 U Uclear clear: : 0.7 t trec1 rec1: : 0.25 U Urec1 rec1: : 0.7 t trec2 rec2: : 0.70 U Urec2 rec2: : 0.9 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 3

  4. FRT REQUIREMENTS FOR ASYNCHRONOUS (PPM) FACILITIES CONNECTED TO THE DISTRIBUTION GRID IN DK1 (CE) AND DK2 (N) Types B, C and D (< 110 kV) facilities Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0.15 t tclear clear: : 0.25 U Uclear clear: : 0.15 t trec1 rec1: : 0.25 U Urec1 rec1: : 0.15 t trec2 rec2: : 0.25 U Urec2 rec2: : 0.9 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 4

  5. FRT REQUIREMENTS FOR SYNCHRONOUS (SGPM) FACILITIES CONNECTED TO THE TRANSMISSION GRID IN DK1 (CE) Type D facilities connected > 110 kV Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0 t tclear clear: : 0.15 U Uclear clear: : 0.6 t trec1 rec1: : 0.15 U Urec1 rec1: : 0.6 t trec2 rec2: : 0.75 U Urec2 rec2: : 0.85 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 5

  6. FRT REQUIREMENTS FOR ASYNCHRONOUS (PPM) FACILITIES CONNECTED TO THE TRANSMISSION GRID IN DK1 (CE) Type D facilities connected > 110 kV Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0 t tclear clear: : 0.15 U Uclear clear: : 0 t trec1 rec1: : 0.15 U Urec1 rec1: : 0 t trec2 rec2: : 0.15 U Urec2 rec2: : 0.85 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 6

  7. FRT REQUIREMENTS FOR SYNCHRONOUS (SGPM) FACILITIES CONNECTED TO THE TRANSMISSION GRID IN DK2 (N) Type D facilities connected > 110 kV Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0 t tclear clear: : 0.15 U Uclear clear: : 0.6 t trec1 rec1: : 0.15 U Urec1 rec1: : 0.6 t trec2 rec2: : 0.75 U Urec2 rec2: : 0.9 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 7

  8. FRT REQUIREMENTS FOR ASYNCHRONOUS (PPM) FACILITIES CONNECTED TO THE TRANSMISSION GRID IN DK2 (N) Type D facilities connected > 110kV Voltage parameters (pu) Voltage parameters (pu) Time parameters [seconds] Time parameters [seconds] U Uret ret: : 0 t tclear clear: : 0.15 U Uclear clear: : 0 t trec1 rec1: : 0.15 U Urec1 rec1: : 0 t trec2 rec2: : 0.15 U Urec2 rec2: : 0.9 t trec3 rec3: : 1.5 16/05118-100 02-07-2019 8

More Related Content

giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#giItT1WQy@!-/#