Resource Integration Topics & Quarterly Stability Assessment Overview
This content provides detailed information on resource integration topics discussed in the ERCOT Resource Integration Working Group. It includes details on Quarterly Stability Assessment (QSA) planning, deadlines, synchronization dates, and issues seen in previous QSAs. Additionally, it covers GINR timelines, active RRs submitted for consideration, and guidelines for AVR testing processes in ERCOT.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Resource Integration Topics Jay Teixeira ERCOT Resource Integration Working Group August 24, 2021
Quarterly Stability Assessment (QSA) Planning Guide 5.9 Next Deadline for QSA All-Inclusive Generation Resource Initial Synchronization Date Upcoming January, February, March Last Day for an IE to meet prerequisites as listed in paragraph (4) below Prior August 1 Completion of Quarterly Stability Assessment End of October Prior November 1 End of January Upcoming April, May, June Prior February 1 End of April Upcoming July, August, September Prior May 1 End of July Upcoming October, November, December If a GINR is not included in QSA, its Initial Synchronization date will be automatically delayed to the next quarter 2
Quarterly Stability Assessment (QSA) Planning Guide 5.9, Quarterly Stability Assessment Issue s seen in previous QSA s 10 day comment period for FIS Needs to be complete before QSA deadline TSPs need to plan for it Dynamic Model Review Dependent on FIS Stability study Need to meet PG 6.9 15 to 30 days prior to QSA deadline PSSE Model Quality Test Required PSCAD Model Quality Test and Unit Model Validation required for November 1, 2021 QSA TSAT Model Required If PSSE model is UDM, then TSAT model should be UDM by November 1, 2021. 3
Active RRs RRGRR028, submitted by John Karlik on behalf of the SPWG on December 23, 2020, Transformer Impedance Clarifications. Language active 9/1. PGRR091, FIS Application Completion 60-Day Limit. Approved by BOD 8/10/2021. PUCT consideration. NOGRR223, Add Phasor Measurement Recording Equipment Requirement to Modified Generating Facilities in Interconnection Process. ROS approved 8/5/2021, IA at ROS 9/2/2021. NOGRR227, Add Phasor Measurement Recording Equipment Location for Main Power Transformer for Intermittent Renewable Resource (IRR). ROS approved 8/5/2021. Next at TAC. 5
New AVR Template Station Code (EXACT): Step 1: Step 2: Step 3: Clear Graph All Clear All Import PI Data Clear Import File ERCOT AVR / PSS Performance Test Guide and Template IRR/IBR AVR Test Process: Coordinate AVR test QSE coordinates with ERCOT and TSP/TO! Start with a few minutes of data with the AVR set point at its neutral or nominal setting. Increase the AVR set-point by 2-4% (not to exceed 1.05 per unit voltage, or a lower value if specified by the Transmission Operator or system conditions) and allow sufficient time for the AVR system response to settle (Minimum 5 minutes). Change the AVR set point back to the nominal set point and allow sufficient time for the AVR system response to settle (Minimum 5 minutes). Decrease the voltage set-point by 2-4% step-change (limited to 0.95pu), depending on the initial set-point voltage and ERCOT s and TSP s feedback on the size of step-change allowable at the time of the test based on system conditions. Allow sufficient time for the AVR system response to settle (Minimum 5 minutes) Change the voltage set-point back to the original set-point Allow sufficient time for the AVR system response to settle (Minimum 5 minutes) Record all the data and submit the AVR test results to ERCOT via NDCRC Record in 1- 4 sec intervals! Conventional AVR/PSS Test Process: Coordinate AVR/PSS test QSE coordinates with ERCOT and TSP/TO! The tests should be performed when the generators under test are on-line and at high or full output If the generator is equipped with a PSS, the PSS should be turned off to verify the functioning and performance of the AVR. Another test should be conducted with the PSS on to verify the functioning and performance of the PSS A voltage set-point step of 2-4% is recommended for the tests (limited to the range of .95pu-1.05pu at the POI) Test data should be collected for at least 1-5 seconds prior to the step change and for at least 10 20 seconds after The test should begin with the AVR voltage set-point at its neutral or nominal setting. The AVR voltage set-point should be changed by introducing the step and allowed to settle, then the AVR voltage set-point should be returned to the setting prior to the step change and allowed to settle Record all the data and submit the AVR and/or PSS test results to ERCOT via NDCRC Record in 1- 4 sec intervals! Voltage Levels Reactive Power Output Real Power Output Capacitors Reactors SVC/STATCOM/S.C. Conventional Generation Gross Unit Reactive Power Output (MVAR) Gross Unit Reactive Power Output (MVAR) Gross Unit Reactive Power Output (MVAR) Gross Unit Reactive Power Output (MVAR) Gross Unit Reactive Power Output (MVAR) Gross Unit Real Power Output (MW) Gross Unit Real Power Output (MW) Gross Unit Real Power Output (MW) Gross Unit Real Power Output (MW) Gross Unit Real Power Output (MW) Actual Volatge at Monitor Terminals (kV) POI MV Bus Voltage (kV) Reactive Power - Capacitor (MVAR) Reactive Power - Capacitor (MVAR) Reactive power - Capacitor (MVAR) Reactive power - Capacitor (MVAR) Reactive power - Capacitor (MVAR) Reactive Power - Reactor (MVAR) Reactive Power - Reactor (MVAR) Reactive Power Dynamic (MVAR) Reactive Power Dynamic (MVAR) Generator Terminal Frequency (Hz) PSS Status [ON] PSS Status [OFF] Time Stamp (Central Standard Time) Point (kV) AVR Set Voltage (kV) 6
DGR Workshop XII September 16, 2021 after PRS meeting Topics for Discussion (tentative) Unboxing PGRR82 language Timeline for lifting moratorium What will RE s need to have ready for January 4, 2022 7
Other contact information ResourceIntegrationDepartment@ercot.com is distribution list for Resource Integration department Mailing List RESOURCE_INTEGRATION@LISTS.ERCOT.COM 8
Questions? Thank you!