Power Transmission and Distribution Network of Tunnel Boring Machine Site
The power transmission and distribution network at the tunnel boring machine (TBM) site involves electrical motors, generators, transformers, and power cables to efficiently operate TBMs for tunnel construction. The system includes multiple generators, transformers, junction boxes, and power distribution components to supply power to TBMs, slurry treatment plants, and other systems on-site. The setup ensures reliable power supply and efficient operation of the equipment involved in the tunneling process.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
E N D
Presentation Transcript
Bultains: Title: Power Transmission and Distribution network of Tunnel Boring Machine site Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
Power Transmission and Distribution Network of Tunnel Boring Machine site Tunnel Boring Machine(TBM) Most of the parts work with use of electrical motors and consumes electrical power, generating electrical power on site with use of generators and connection also with government supply, this supply(11KV) reach to TBM after synchronization of generators with use of power cables and junction boxes, Step down this power with use of Transformer(11KV/690-400V) and Consuming this power for operation of TBM. Hypothetic example: Two TBMs was on site, each TBM was 3200KVA load and 6000kVA load for Surface, Slurry Treatment Plant and Slurry Transportation System. For each TBM three 2000KVA generators are using, in this one generator for maintenance and four 2000KVA generators using for Surface, STP and STS loads, in this one generator for maintenance. Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
Power Transmission and Distribution Network of Tunnel Boring Machine site 3200KVA 11KV/680/400V 680/400V 11KV 11KV Generator-1 2000KVA, 400V 11KV TBM-1 Transformer with HT Breaker 4000KVA,440/11kv HT TBM Step Down Transformer HT Cable Drum Power Distribution HT Junction Box/Joint Generator-2 2000KVA, 400V Breaker Generator-3 2000KVA, 400V Generator-4 2000KVA, 400V 3200KVA 11KV/680/400V 11KV 11KV 11KV 680/400V Generator-5 2000KVA, 400V TBM-2 Transformer with HT Breaker 4000KVA,440/11kv Synchronization panel HT TBM Step Down Transformer HT Cable Drum Power Distribution HT Junction Box/Joint Breaker Generator-6 2000KVA, 400V Generator-7 2000KVA, 400V Tunnel & TBM Generator-8 2000KVA, 400V 6000KVA 11KV/680/400V 680/400V 11KV 11KV Generator-9 2000KVA, 400V Surface/STP Transformer with HT Breaker 6000KVA,440/11kv HT HT Step Down Transformer Power Distribution Junction Box/Joint Breaker Generator-10 2000KVA, 400V Located on the Surface Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
Power Transmission and Distribution Network of Tunnel Boring Machine site Generator-1 2000KVA, 400V Step Down Transformer 3200KVA/11K V/680/400V TBM-1 Transformer with HT Breaker 4000KVA,440/11kv HT Synchronization panel HT Cable Drum Power Distribution HT Junction Box/Joint Generator-2 2000KVA, 400V Breaker Generator-3 2000KVA, 400V Generator-4 2000KVA, 400V Generator-5 2000KVA, 400V TBM-2 Transformer with HT Breaker 4000KVA,440/11kv Step Down Transformer 3200KVA/11K V/680/400V HT Synchronization panel HT Cable Drum Power Distribution HT Junction Box/Joint Breaker Generator-6 2000KVA, 400V Tunnel & TBM Generator-7 2000KVA, 400V Generator-8 2000KVA, 400V Step Down Transformer 6000KVA/11KV/680 /400V Generator-9 2000KVA, 400V Surface/STP Transformer with HT Breaker 6000KVA,440/11kv HT Synchronization panel Power Distribution HT Junction Box/Joint Breaker Generator-10 2000KVA, 400V Located on the Surface Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
Power Transmission and Distribution Network of Tunnel Boring Machine site TBM-1 Sub-Station HT HT Power Distribution Step Down Transformer HT Cable Drum Junction Box/Joint Breaker 11KV 11KV 3200KVA 11KV/680/400V Substation with Capacity of 10MVA Transformer with HT Breaker 680/400V 11KV Power Supply from Government 33KV or 11KV TBM-2 HT HT Power Distribution Step Down Transformer HT Cable Drum Junction Box/Joint Breaker Substation with Capacity of 6MVA Transformer with HT / LT Breaker 11KV 680/400V 3200KVA 11KV/680/400V 11KV 11KV Surface & STP Emer.Generator-1 1000KVA, 400V Power Distribution to Surface loads and STP loads Power - Change Over Emer.Generator-2 1000KVA, 400V 680/400V Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
Power Transmission and Distribution Network of Tunnel Boring Machine site Emergency Generators loads: Ventilation Fans for Two Tunnel Boring Machines Tunnel, Surface Lighting Compressors for two TBM s located on Surface De-watering Systems Grout plant cleaning Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use
END Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use Sensitivity: LNT Construction Internal Use