ERCOT's upcoming market releases carry higher risk and complexity, requiring system design changes impacting all QSE AS Offers. Weekly Market Readiness meetings will address necessary testing, scorecards, and cutover approaches. SME calls will provide technical and business support. Required MOTE participation aims for operational continuity amidst structural changes.

  • ERCOT
  • Market Readiness
  • Weekly Meetings
  • Risk Management
  • Energy

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Weekly Market Readiness for FFRA and Firm-Fuel Release (Go-Live October 13, 2022) Matt Mereness October 11, 2022

  2. Outline Purpose and scope of weekly Market Readiness meetings Required testing and scorecard for QSEs in MOTE Other supplemental information as needed or requested Data Cutover Approach Summary and Q&A Appendix High level review of transaction changes 2 PUBLIC

  3. Purpose and scope of weekly Market Readiness meetings ERCOT s release for October 13, 2022 carries more risk and complexity than releases in recent years: Required system design changes to Ancillary Service (AS) Offers that structurally impacted all QSE AS Offers and is not backward compatible. Risk- inability to submit AS Offers due to interface issues would affect ERCOT reliability Other transactions for RRS-related submissions are also impacted: Current Operating Plan (COP) new columns required AS Self-Arrangement value changes AS Trades value changes On the day of implementation/cutover, QSEs may be required to cancel and re-submit certain transactions (later agenda item) ERCOT will host these weekly calls with SMEs to answer technical and business questions, or to follow up with additional information as needed. Note- although not as high risk, the MOTE deployment also supports changes to Firm Fuel awarded providers (Availability Plan). Firm Fuel software deployment is October 13, 2022 for Nov 15, 2022 Operating Day. 3 PUBLIC

  4. Purpose and scope of weekly Market Readiness meetings (continued) Progression of Market Readiness: FFRA Interface changes reviewed at December 7, 2021 workshop Updates at every TWG meeting Market Notice concerning Market Readiness May 20, 2022 Interface changes are not backward compatible. All QSEs that are qualified providers of Responsive Reserve Service (RRS), Regulation Service, and/or Non-Spinning Reserve Service will be required to demonstrate their ability to submit offers for these Ancillary Services using the new interface prior to implementation of the FFRA project Project/Business review at July 25, 2022 workshop MOTE deployment- August 15, 2022 MOTE participation required, monitored, and published by ERCOT. (Aug 15 Aug 26): No submission summary published Weeks 1 & 2 (Aug 29 Sep 9): Publish weekly submission summary by QSE (target 50% success) Weeks 3 & 4 (Sep 12 Sep 23): Publish weekly submission summary by QSE (target 75% success) Week 5 & 6 (Sept 26 Oct 7): Publish weekly submission summary by QSE (target 95% success) Weekly Market Readiness- every Tuesday, 10am Aug 30-Oct 11, 2022 FFRA Go-Live October 13, 2022 (approx. 9pm) 4 PUBLIC

  5. Required testing and scorecard for QSEs in MOTE All QSEs highly encouraged to test in MOTE at their own pace With the COP structural changes from FRRA, all QSEs with Resources should submit into MOTE to ensure successful operations continuity (even if not RRS providers). Required participation for QSEs that submitted AS Offers May 15 through Aug 15, 2022 will be monitored and published to TAC. MOTE participation targets for required QSE AS Offers: (Aug 15 Aug 28): No submission summary published Weeks 1 & 2 (Aug 29 Sep 11): Publish weekly submission summary by QSE (target 50% success) Weeks 3 & 4 (Sep 12 Sep 25): Publish weekly submission summary by QSE (target 75% success) Week 5 & 6 (Sept 26 Oct 9): Publish weekly submission summary by QSE (target 95% success) The list of required QSEs is in scorecard and posted with presentation For 56 QSEs, ERCOT is tracking each QSE that submitted submit at least one AS Offer during the week for each service that they offered in the 90-day window May15-Aug15. Green = All AS types historically offered were submitted at least once during week Yellow = Some, but not all, types of AS Offers submitted Red = No AS Offers submitted If you need assistance identifying which Ancillary Services your company submitted May 15 Aug 15, please contact Matt.Mereness@ercot.com 5 PUBLIC

  6. Required testing and scorecard for QSEs in MOTE Goal is 95%, currently at 96% (CONGRATS!) List/Snapshot of QSEs that historically submitted AS Offers May 15 - August 15, 2022 G Y R All AS types historically offered were submitted at least once during week Some, but not all types of AS Offers submitted No AS Offers submitted Cumulative Score G G G G G G G G Y Y G R G Y Y Y Y Y Y Y G G G G R G G G G PARTICIPANT_NAME QAEN QBEEP1 QBEEPO QBRAZP QBROAD QBTU QCALP QCPSE QDENT2 QDUKER QECNR QECTOR QEDE20 QEDE21 QEDES3 QEDF20 QEDF22 QEDF23 QEDF26 QEDF39 QEDIS9 QENDU2 QENEL5 QENEL6 QENROC QENRWI QEONG3 QEXELO QFPL12 MP_FULLNAME CITY OF AUSTIN DBA AUSTIN ENERGY (QSE) HEN POWER MARKETING LLC (SQ1) HEN POWER MARKETING LLC (QSE) BRAZOS ELECTRIC POWER CO OP INC POST (QSE) BROAD REACH POWER LLC (QSE) BTU QSE SERVICES INC (QSE) CALPINE POWER MANAGEMENT LLC (QSE) CPS ENERGY (QSE) DENTON MUNICIPAL ELECTRIC (SQ2) DUKE ENERGY RENEWABLE SERVICES LLC (QSE) RWE RENEWABLES QSE LLC (QSE) ECTOR COUNTY ENERGY CENTER LLC (QSE) EDF ENERGY SERVICES LLC (SQ20) EDF ENERGY SERVICES LLC (SQ21) EDF ENERGY SERVICES LLC (SQ3) EDF NORTH AMERICA (SQ20) EDF NORTH AMERICA (SQ22) EDF NORTH AMERICA (SQ23) EDF NORTH AMERICA (SQ26) EDF NORTH AMERICA (SQ39) BOSTON ENERGY TRADING AND MARKETING LLC (SQ9) ETC ENDURE ENERGY LLC LAAR (SQ2) ENEL TRADING NORTH AMERICA LLC (SQ5) ENEL TRADING NORTH AMERICA LLC (SQ6) ENEL X NORTH AMERICA INC (QSE) ENERWISE GLOBAL TECHNOLOGIES LLC (QSE) UNIPER GLOBAL COMMODITIES NORTH AMERICA LLC (SQ3) CONSTELLATION ENERGY GENERATION LLC (QSE) NEXTERA ENERGY MARKETING LLC (SQ12) QGAR QGAR14 QGEUS QLCRA QLUMN QM2SQ1 QMCADO QMP2EN QNRGT4 QNRGTX QOCCID QPERFT QPRIO1 QPRIOR QSANDY QSHEL2 QSTEC QSTEC3 QSUE23 QTEN20 QTEN22 QTEN23 QTEN25 QTENS4 QTENS7 QTENSK QTURKY CITY OF GARLAND (QSE) CITY OF GARLAND (SQ14) GEUS (QSE) LOWER COLORADO RIVER AUTHORITY (QSE) LUMINANT ENERGY COMPANY LLC (QSE) MP2 ENERGY LLC (SQ1) MCADOO WIND ENERGY LLC (QSE) MP2 ENERGY LLC (QSE) NRG TEXAS CEDAR BAYOU (SQ4) NRG TEXAS POWER LLC (QSE) OCCIDENTAL POWER SERVICES INC (QSE) PERFECT POWER SOLUTIONS TEXAS LLC (QSE) PRIORITY POWER MANAGEMENT LLC (SQ1) PRIORITY POWER MANAGEMENT LLC (QSE) SANDY CREEK ENERGY ASSOCIATES LP (QSE) SHELL ENERGY NORTH AMERICA (US) LP (SQ2) SOUTH TEXAS ELECTRIC CO OP INC (QSE) SOUTH TEXAS ELECTRIC CO OP INC (SQ3) ENGIE ENERGY MARKETING NA INC (SQ23) TRQ20 (SQ20) TRQ22 (SQ22) TRQ23 (SQ23) TRQ25 (SQ25) TRQ4 (SQ4) TRQ7 (SQ7) TENASKA POWER SERVICES CO (QSE) TURKEY TRACK WIND ENERGY LLC (QSE) G G G G G G G G G G G G G G G G G G G G G G G G G G G Weekly posting on TAC homepage: https://www.ercot.com/committees/tac 6 PUBLIC

  7. COP Outreach Message sent 2 weeks ago to all QSEs with Resources that have not submitted a COP into MOTE: 7 PUBLIC

  8. Other Supplemental Information: Firm Fuel Supply Service Change Changes limited to QSEs awarded FirmFuel that will submit Availability Plans New Availability Plan type = FFSS Note that Firm Fuel software deployment is October 13, 2022 for Nov 15, 2022 Operating Day QSEs can request FFSS Resource qualification in MOTE by requesting from Matt.Mereness@ercot.com and/or through your ERCOT Account Manager or email ClientServices@ercot.com Question/Answer from last week: Will the new Settlement billing determinants for NPRR1120 be included in the settlement extracts reports on October 13 2022? Or will they start showing up on November 15? Data will start showing up on extracts for operating Day November 15th Does ERCOT have any Mock Settlement statements for NPRR1120? No Are there new invoices associated with NPRR1120? No, it s a new charge type on the existing Real Time Statement 8 PUBLIC

  9. Data Cutover Approach Planned cutover is evening of October 13, 2022 (at approximately 9pm) Before October 13 evening upgrade: On morning of October 13, DAM completes and publish awards at 1330 for OD Oct 14 (current system and RRS). DRUC, HRUC, SASM continue to run on old code most of day. QSE action before evening of cutover on October 13: After cutover, queries and cancels are not backward compatible for AS Trades, AS Offers, AS Self- Arrangement, therefore .. If exists where QSE submitted OD+2 (Oct 15), then QSE must cancel AS Offers and AS Self-Arrangement with RRS for OD 10/15 and forward before the upgrade (some QSEs submit OD+2 and beyond). QSEs will not be able to Query AS Trades in old format after upgrade, if needed then recommend QSE query AS Trades for snapshot of confirmed trades before upgrade. After upgrade on Oct 13 evening: Immediately QSEs will need to refresh COP submissions that contain RRS QSE AS Trades submitted after cutover will be new RRS types QSE AS Offers and AS Self-Arrangement after cutover for morning of 10/14 for DAM OD 10/15 will be new RRS types More detail on subsequent slides for each transaction type . 9 PUBLIC

  10. COP cutover System Cutover OD Oct 12 OD Oct 13 OD Oct 14 OD Oct 15 OD 10/12 Normal COP submission for next 7 days OD 10/13 Normal COP submission for next 7 days AFTER CUTOVER on 10/13 (at approximately 9pm) RE-SUBMIT COPs for Resources carrying RRS for next OD 10/14 0100 and forward Update- ERCOT will be able to accept any balance of day 10/13 HE 2300, 2400 OD 10/14 Normal COP submission on new COP structure OD 10/15 Normal COP submission on new COP structure 10 PUBLIC

  11. AS Self-Arrangement cutover System Cutover OD Oct 12 OD Oct 13 OD Oct 14 OD Oct 15 OD 10/12 Normal AS Self-Arrangement (DAM for OD 10/13) Note- Do not submit AS Self-Arrangement for DAM OD 10/15 and beyond OD 10/13 Normal AS Self-Arrangement (DAM for OD 10/14) Note- Do not submit AS Self-Arrangement for DAM OD 10/15 and beyond AFTER CUTOVER on 10/13, no special activities required OD 10/14 AS Self-Arrangement (DAM for OD 10/15) on new RRS Sub Types OD 10/15 AS Self-Arrangement (DAM for OD 10/16) on new RRS Sub Types 11 PUBLIC

  12. AS Offers cutover System Cutover OD Oct 14 (transition, no SASM) OD Oct 12 OD Oct 13 OD Oct 15 OD 10/12 Normal AS Offers (DAM for OD 10/13) Note- Do not submit AS Offers for DAM OD 10/15 and beyond OD 10/13 Normal AS Offers (DAM for OD 10/14) Note- Do not submit AS Offers for DAM OD 10/15 and beyond AFTER CUTOVER on 10/13, no special activities required OD 10/14 AS Offers (DAM for OD 10/15) on new RRS Sub Types OD 10/15 AS Offers (DAM for OD 10/16) on new RRS Sub Types For OD 10/14 ERCOT will not be running RSASM or SASM. If AS is needed, Control Room will follow procedures for a failed SASM. 12 PUBLIC

  13. AS Trades cutover System Cutover OD Oct 12 OD Oct 13 OD Oct 14 (transition day) OD Oct 15 OD 10/14 will maintain already submitted trades from old transaction, and accept new transactions OD 10/15 incompatible with pre-upgrade AS Trades OD 10/12 Normal AS Trades (EXCEPT DO NOT submit for OD 10/15 (OD+3) and beyond) OD 10/13 Normal AS Trades for most of day, EXCEPT DO NOT submit RRS-AS-Trades for OD 10/15 (OD+2) and beyond. After upgrade QSE will not be able to Query or Cancel RRS-AS-Trades from old submissions Highly recommend taking snapshot of confirmed RRS-AS-Trades before cutover (if dependent on ERCOT portal for AS Trades) RRS-AS-Trades that are submitted after cutover can be queried and cancelled on OD 10/14 OD 10/14 (transition day) AS Trades can be entered with new RRS-sub-types QSE will not be able to Query or Cancel RRS-AS-Trades from old submissions ERCOT will provide market notice for considering RRS-AS-Trade cancellations, or both QSEs follow dispute process. OD 10/15 Normal AS Trades 13 PUBLIC

  14. QSE Readiness risk mitigation Questions have come up regarding what if my QSE is not ready, will the upgrade be deferred ? The short answer is No, the upgrade will proceed but: ERCOT will be reaching out to individual QSEs to understand why not testing in MOTE, or why not ready. MITIGATION: In MOTE and after the cutover, QSEs have option of using Portal Interface / MMS-UI as alternative interface for market submissions. 14 PUBLIC

  15. Draft Market Notice going out today (2 slides) NOTICE DATE: October 11, 2022 NOTICE TYPE: M-xxx Operations SHORT DESCRIPTION: Market Readiness support for QSEs during implementation of the Fast-Frequency Response (FFR) Advancement project and Partial Implementation of NPRR863, NPRR1015, NPRR1079, and NOGRR187 INTENDED AUDIENCE: ERCOT Market Participants DAYS AFFECTED: October 13, 2022 and October 14, 2022 LONG DESCRIPTION: Details are provided below to summarize and assist QSEs during the operational and system cutover activities later this week in support of the FFRA project and accompanying interface changes. Timing: - The upgrade is planned to occur between 7pm and 9pm on Thursday, October 13, 2022 Communication: - ERCOT Control Room will use the QSE Hotline call for communications before and after the upgrade is complete. - ERCOT will also post an Operations Message after the upgrade is complete requesting all QSEs to update their Current Operating Plan for Resources carrying Response Reserve Services as soon as possible. - ERCOT will be staffing 24-hour coverage for receiving emails with any market submission questions or technical issues using ClientServices@ercot.com from October 13, 2022 5:00pm to October 14, 2022 5:00pm. 15 PUBLIC

  16. Draft Market Notice going out today (2 slides) Reminder of technical and business process changes: - Current Operating Plans (COPs): After October 13, 2022 9:00pm, the COP transaction includes three subtypes for Response Reserve Services (RRSPF, RRSFF, RRSUF). - Ancillary Service Trades (AS Trades): October 14, 2022 is the first Operating Day for new AS Trade types (RRSPF, RRSFF, RRSUF), which replace the current AS Trade types (RRSGN, RRSLD, RRSNC). October 14, 2022 is the only Operating Day that will support both the old and new trade types. Note that after the upgrade on October 13, 2022 at 9:00pm, QSEs will not be able to query or cancel trades for the old types due to the implemented interfaces. In the event a trade needs to be cancelled, both parties in the AS Trade can contact ClientServices@ercot.com for assistance. - Ancillary Service Offers and Ancillary Service Self-Arrangement: Day-Ahead Market Operations occurring on October 14, for Operating Day October 15 will be the first Day-Ahead Market using the three new subtypes for RRS (RRSPF, RRSFF, RRSUF). - ERCOT will not execute the daily Reconfiguration Supplemental Ancillary Service Market (RSASM) for OD October 14, 2022 due to the system upgrade. Support and Mitigation during Cutover: - ERCOT will be staffing 24-hour coverage for receiving emails with any market submission issues or technical issues using ClientServices@ercot.com. - QSEs that are experiencing submission issues can also utilize the Market Management User Interface (MMS-UI) as an alternate data entry tool. Further support information is available: - ERCOT hosted workshop on July 25, 2022 to outline the implementation details related to this project. - Weekly Market Readiness Meetings have been providing further details. The link to the most recent Weekly Market Readiness meeting is located here. 16 PUBLIC

  17. Summary and Q&A THANK YOU FOR THE SUPPORT AND QUESTIONS Market Notice will be released this afternoon We will be standing by Thursday night to support you! Normal recap: Weekly meetings (ERCOT calendar) Tuesdays 10am Aug 30-Oct 11, 2022 Detailed business changes posted at July 25, 2022 workshop MOTE Scorecard to be published to TAC homepage Weekly emails to TAC Cutover details ERCOT continue to discuss cutover and take questions. ERCOT open to feedback/questions for this or next meeting Feedback can be directed to Matt.Mereness@ercot.com MOTE set-up questions go through your ERCOT Account Manager or email ClientServices@ercot.com Questions? 17 PUBLIC

  18. APPENDIX Specific Interface Changes 18 PUBLIC

  19. Other Supplemental Information High level review of transaction changes Reminder: New RRS Subtypes implemented October 13, 2022 RRS Primary Frequency Response (RRSPF) Analogous to previous RRSGN + RRSLD RRS Load Resources controlled by high-set under-frequency relays (RRSUF) Analogous to previous RRSNC RRS - Fast Frequency Response (RRSFF) Responds within 15 cycles after frequency meets or drops below a preset threshold (59.85 HZ) Sustained for at least 15 minutes, recovers in 15 minutes Can be offered by qualifying Energy Storage (ESR) GEN and CLR, GEN (non ESR), CLR (non ESR), and NCLR. 19 PUBLIC 19

  20. Other Supplemental Information: COP Changes COP AS Resource Responsibility RRS Will be replaced by the new RRS subtypes: RRSPF RRSFF RRSUF Note the extension of RRS-types to 3 fields/headers affects all COPs for all QSEs and encouraged to test COP to minimize cutover risk (20% tested) Note: Submit OD +2 20 PUBLIC 20

  21. Other Supplemental Information: Self-Arranged AS Changes Previous RRS AS Self Arrangement types: RRSGN, RRSLD, and RRSNC Will be replaced by new RRS subtypes: RRSPF, RRSFF, and RRSUF Note: AS Obligation for RRS will continue being reported as RRS obligation, not by new subtypes. Note: Submit OD +2 21 PUBLIC 21

  22. Other Supplemental Information: AS Trades RRS AS Trade types RRSGN, RRSLD, and RRSNC will be replaced by RRSPF, RRSFF, and RRSUF. - RRSFF responsibility can be replaced by any other RRS subtype. - RRSUF responsibility can be replaced by RRSPF or RRSUF. - RRSPF responsibility can only be replaced with other RRSPF. - Note: Submit OD +2 22 PUBLIC 22

  23. Other Supplemental Information: AS Offer Changes For Online Reserves (ONRES), RRS price will be removed and replaced a separate price column for each RRS Subtype. The price columns for ONRES will be as follows: REGUP Price (e.g. PRICE1_REGUP, PRICE2_REGUP PRICE5_REGUP) RRSPF Price (e.g. PRICE1_RRSPF, PRICE2_RRSPF PRICE5_RRSPF) RRSFF Price (e.g. PRICE1_RRSFF, PRICE2_RRSFF PRICE5_RRSFF) RRSUF Price (e.g. PRICE1_RRSUF, PRICE2_RRSUF PRICE5_RRSUF) ONNS Price (e.g. PRICE1_ONNS, PRICE2_ONNS PRICE5_ONNS) NCLR Flag option will be removed Note: Submit OD +2 23 PUBLIC 23

  24. Other Supplemental Information: AS Awards Changes DAM and SASM RRS awards will now be reported by subtype (RRSPF, RRSFF and RRSUF) instead of by RRS. UPDATE: ERCOT provided a sample XML Award at last week s meeting https://www.ercot.com/calendar/event?id=1661527566189 Note: RRS MCPC will remain as RRS . 24 PUBLIC 24

  25. Other Supplemental Information: Telemetry changes Extra telemetry points have already been added into production supporting AS Responsibility and AS Schedule for RRS-FFR Existing Ancillary Service Responsibility and Ancillary Service Schedule telemetry for RRS-PFR and RRS-UFR will continue to be used (no change) New points added for RRS-FFR Table 19- Non Controllable Load Resource / LR / Table 20- Generation Unit / UN / Table 20- Generation Unit / UN / Table 20- Non-Controllable Load Resource / LR / Table 20- Non-Controllable Load Resource / LR / FFR Deployed / FDPL (status) FFR Responsibility / FFRS FFR Schedule / FFSC FFR Responsibility / FFRS FFR Schedule / FFSC ICCP Handbook: https://www.ercot.com/gridinfo/transmission (Bottom of the webpage) Email: ErcotICCPSupport@ercot.com 25 PUBLIC 25