Development Update for Brent Terrace Project: Plots 53 & 54

Slide Note
Embed
Share

Providing an update on the Brent Terrace project, focusing on Plots 53 and 54. The team introductions, details of the new homes, communication strategy with residents, site surveys in progress, potential impact on residents, and mitigation measures being implemented are discussed. Measures include managing increased vehicle movements, noise, dust, and vibrations. Residents can expect regular communication, consultation events, and mitigation strategies to address any disturbances caused by the construction activities.


Uploaded on Oct 06, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Plots 53 & 54, Brent Terrace

  2. Introductions Chris Thwaite Construction Manager Karl David - Project Manager Gary Akers - Snr Design & Technical Manager Paul Davies - Design & Technical Manager Simone Taylor Regeneration Coordinator Toni Hodson Ass. Project Manager 2

  3. Plots 53 & 54 47 new homes for existing Whitefields Estate residents 3

  4. Plots 53 & 54 4

  5. Plots 53 & 54 Plot 53 30 Homes Plot 54 17 Homes 5

  6. Communications Strategy with Whitefield & Brent Terrace Residents Following L&Q starting on site there will be: Regular Surgeries Regular Newsletters Site Noticeboard Attend & Update Residents Meetings Consultation Events: Meet the team opportunities Resident Liaison: One point of contact for resident queries. 6

  7. Site Surveys What are we doing now? Designing the foundations Undertaking surveys - Boreholes to determine the ground beneath the site - Drainage investigations Further surveys to be completed Earth bunds to be reinstated 7

  8. Potential Impact for Residents Increased vehicle movements Noise Dust & Vibration Parking Unloading and distribution 8

  9. Mitigation Measures Vehicle Movements Traffic Marshalls available Deliveries on smaller vehicles Deliveries outside of peak times Off site holding area Delivery booking in system 9

  10. Mitigation Measures - Noise Works within agreed hours Machinery switched off when not in use Acoustic shielding for particular noisy activity Silenced plant Prefabrication/off site manufacture No Radios on site Out of hours working only where agreed in advance 10

  11. Mitigation Measures Dust & Vibration Damping down during dry spells of weather Road sweeping undertaken at regular intervals Skips kept covered Any cutting undertaken with water spray Vibrating equipment used only where necessary Cutting and sawing used rather than breaking out Methodology avoids vibration & dust creation 11

  12. Mitigation Measures Parking Parking management strategy to be produced Parking limitations advised in orders Parking controlled by site management Subcontractors penalised where infringements Shared use of vehicle scheme Use of public Transport promoted 12

  13. Mitigation Measures Unloading & Distribution Deliveries unloaded in site boundary where possible Delivery restrictions advised in orders Forklift to distribute materials around site Deliveries made via new access roadway Vehicles leave site via new access roadway 24 Hr notice for deliveries 7 day notice for larger deliveries 13

  14. Access to the Surrounding Area 14

  15. Access to the Surrounding Area 15

More Related Content