Development Update for Brent Terrace Project: Plots 53 & 54

Plots 53 & 54, Brent Terrace
2
Introductions
 
Chris Thwaite – Construction Manager
  
Karl David - Project Manager
Gary Akers -  Snr Design & Technical Manager
Paul Davies - Design & Technical Manager
Simone Taylor – Regeneration Coordinator
Toni Hodson – Ass. Project Manager
Plots 53 & 54
47 new homes for existing Whitefields Estate residents
3
Plots 53 & 54
 
4
Plots 53 & 54
Plot 53 – 30 Homes
Plot 54 – 17 Homes
5
Communications Strategy with Whitefield & Brent
Terrace Residents
Following L&Q starting on site there will be:
Regular Surgeries
Regular Newsletters
Site Noticeboard
Attend & Update Residents Meetings  
Consultation Events: 
Meet the team opportunities
Resident Liaison: 
One point of contact for resident
queries.
6
Site Surveys
What are we doing now?
Designing the foundations
Undertaking surveys
 
- Boreholes to determine the ground beneath the site
 
- Drainage investigations
Further surveys to be completed
Earth bunds to be reinstated
7
Potential Impact for Residents
Increased vehicle movements
Noise
Dust & Vibration
Parking
Unloading and distribution
8
Mitigation Measures – Vehicle Movements
Traffic Marshalls available
Deliveries on smaller vehicles
Deliveries outside of peak times
Off site holding area
Delivery booking in system
9
Mitigation Measures - Noise
Works within agreed hours
Machinery switched off when not in use
Acoustic shielding for particular noisy activity
Silenced plant
Prefabrication/off site manufacture
No Radios on site
Out of hours working only where agreed in advance
10
Mitigation Measures – Dust & Vibration
Damping down during dry spells of weather
Road sweeping undertaken at regular intervals
Skips kept covered
Any cutting undertaken with water spray
Vibrating equipment used only where necessary
Cutting and sawing used rather than breaking out
Methodology avoids vibration & dust creation
11
Mitigation Measures – Parking
Parking management strategy to be produced
Parking limitations advised in orders
Parking controlled by site management
Subcontractors penalised where infringements
Shared use of vehicle scheme
Use of public Transport promoted
12
Mitigation Measures – Unloading & Distribution
Deliveries unloaded in site boundary where possible
Delivery restrictions advised in orders
Forklift to distribute materials around site
Deliveries made via new access roadway
Vehicles leave site via new access roadway
24 Hr notice for deliveries
7 day notice for larger deliveries
13
Access to the Surrounding Area
 
14
Access to the Surrounding Area
15
Slide Note
Embed
Share

Providing an update on the Brent Terrace project, focusing on Plots 53 and 54. The team introductions, details of the new homes, communication strategy with residents, site surveys in progress, potential impact on residents, and mitigation measures being implemented are discussed. Measures include managing increased vehicle movements, noise, dust, and vibrations. Residents can expect regular communication, consultation events, and mitigation strategies to address any disturbances caused by the construction activities.

  • Development update
  • Brent Terrace project
  • Plots 53 & 54
  • Construction management
  • Resident communication

Uploaded on Oct 06, 2024 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. Download presentation by click this link. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

E N D

Presentation Transcript


  1. Plots 53 & 54, Brent Terrace

  2. Introductions Chris Thwaite Construction Manager Karl David - Project Manager Gary Akers - Snr Design & Technical Manager Paul Davies - Design & Technical Manager Simone Taylor Regeneration Coordinator Toni Hodson Ass. Project Manager 2

  3. Plots 53 & 54 47 new homes for existing Whitefields Estate residents 3

  4. Plots 53 & 54 4

  5. Plots 53 & 54 Plot 53 30 Homes Plot 54 17 Homes 5

  6. Communications Strategy with Whitefield & Brent Terrace Residents Following L&Q starting on site there will be: Regular Surgeries Regular Newsletters Site Noticeboard Attend & Update Residents Meetings Consultation Events: Meet the team opportunities Resident Liaison: One point of contact for resident queries. 6

  7. Site Surveys What are we doing now? Designing the foundations Undertaking surveys - Boreholes to determine the ground beneath the site - Drainage investigations Further surveys to be completed Earth bunds to be reinstated 7

  8. Potential Impact for Residents Increased vehicle movements Noise Dust & Vibration Parking Unloading and distribution 8

  9. Mitigation Measures Vehicle Movements Traffic Marshalls available Deliveries on smaller vehicles Deliveries outside of peak times Off site holding area Delivery booking in system 9

  10. Mitigation Measures - Noise Works within agreed hours Machinery switched off when not in use Acoustic shielding for particular noisy activity Silenced plant Prefabrication/off site manufacture No Radios on site Out of hours working only where agreed in advance 10

  11. Mitigation Measures Dust & Vibration Damping down during dry spells of weather Road sweeping undertaken at regular intervals Skips kept covered Any cutting undertaken with water spray Vibrating equipment used only where necessary Cutting and sawing used rather than breaking out Methodology avoids vibration & dust creation 11

  12. Mitigation Measures Parking Parking management strategy to be produced Parking limitations advised in orders Parking controlled by site management Subcontractors penalised where infringements Shared use of vehicle scheme Use of public Transport promoted 12

  13. Mitigation Measures Unloading & Distribution Deliveries unloaded in site boundary where possible Delivery restrictions advised in orders Forklift to distribute materials around site Deliveries made via new access roadway Vehicles leave site via new access roadway 24 Hr notice for deliveries 7 day notice for larger deliveries 13

  14. Access to the Surrounding Area 14

  15. Access to the Surrounding Area 15